Road - Construction Work
Zoneअंचल
Divisionमंडल
Categoryश्रेणी
Work Typeकार्य का प्रकार
S. No.क्र. सं. Name of Workकार्य का नाम Date of Startकार्य आरम्भ करने की तिथि Date of Completionकार्य समाप्त करने की तिथि Cost
(In Lac)
Expenditure
(In Lac)
Progress Agency Status Viewदेखें
1 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 2015.04.18 2017.10.17 96400.00 137425.16 (Oct'22) 0.00 (Oct'22) Larson & Toubro Limited Work in progress Detail Report
Graph / Photo
2 Extension of Ashram Flyover to DND Flyover. 2020.06.19 2021.06.18 12879.00 12667.40 (Oct'22) 0.00 (Oct'22) KCC Buildcon Pvt. LTD The work was delayed due to restriction of COVID-19 & non approval of traffic NOC. Now, the work in central portion has just started after receipt of Phase-II NOC on 24.09.2021. Now, the progress is at the desired pace. Subway finishing work is in progress. The FOB & Electrical work in progress.Extension of time is submitted in the office of CE (Flyover) for extension up to 13.11.2022. Detail Report
Graph / Photo
3 Construction of Bridge on Najafgarh Drain at Tri Nagar/Inderlok, Karampura and Rampura, Delhi to cover the complete Right of Way (ROW) excluding area of already constructed bridge alongwith road improvement on either side of bridge including making. 2019.03.16 2021.09.30 5388.53 5589.93 (Aug'22) 0.00 (Aug'22) Ram Kumar Contractor work is in progress Detail Report
Graph / Photo
4 Construction of underpass along Mathura Road at Ashram Chowk New Delhi 2019.07.05 2020.07.04 4907.38 6043.94 (Aug'22) 0.00 (Aug'22) Dharamraj Contracts (I) Pvt. Ltd. The work was delayed due to restriction of COVID-19 wave 1 & subsequently wave 2. The work is nearing completion. The underpass has been opened for traffic on 24.04.2022. The FOB & Electrical work in progress. Detail Report
Graph / Photo
5 C/o Three Lane Flyover, Road Work, Footpath, Drainage System, Landscaping, Railing, Road Signages, Street Light & Allied works. 2022.07.15 2023.07.14 4199.50 499.99 (Oct'22) 0.00 (Oct'22) Gawar Construction Ltd., Work recently awarded Detail Report
Graph / Photo
6 Covering of the ramps of all the underpass (entry & exit) i.e. Underpass 1 to 6 as well as the main tunnel entry and exit ramps, branch tunnel entry ramps developed in the construction of Integrated Transit Corridor Development plan in and around Pragati Maidan. 2022.05.21 2022.11.20 4144.69 R S Sharma Contractors Pvt. Ltd. Detail Report
Graph / Photo
7 W/O Mahrauli Mahipalpur Road. SH: from 4 lanes to 8 lanes and Service Road from Andheria More to Masoodpur Village. 2012.10.30 2013.04.29 3812.11 KCC Buildcon Pvt. LTD . Detail Report
Graph / Photo
8 Construction of Bridge on Supplementary Drain on NH-10, Nangloi, Delhi to cover complete width of 60 m with road improvement in 100 meter length on either side of bridge including making of drainage scheme, footpath etc. complete (after dismantling ). 2019.03.06 2020.12.05 3350.31 0.00 (Sep'22) 86.00 % (Sep'22) Ram Kumar Contractor Traffic on newly constructed bridge (upstream & downstream side) had already been diverted. Dismantling of existing bridge and all piling work have been completed. Pile cap work is in progress. Detail Report
Graph / Photo
9 Strengthening of SSN Marg ID- 392 and 100 Foota Road ID- 1187 New Delhi. 2020.09.10 2021.01.09 1893.62 3407.76 (Oct'22) 0.00 (Oct'22) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
10 Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi 2021.11.22 2022.10.17 1773.27 827.53 (Oct'22) 0.00 (Oct'22) Harbel Singh & Sons The work in progress.. Detail Report
Graph / Photo
11 Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) 2022.09.17 2022.12.15 861.04 SBG Infracon Pvt Ltd Detail Report
Graph / Photo
12 Construction of Pedestrian Underpass Subway Across Aurobindo Marg Between Delhi Haat and Entry No 4 of East Kidwai Nagar. 2020.10.27 2021.08.26 856.26 55.63 (Jun'22) 0.00 (Jun'22) M/s Satish Builders Initially the work was delayed due to restriction of COVID-19. Work is in progress in Delhi HAAT side & NBCC side entry / exit. The traffic in central portion has been opened after construction of box. The shifting of NDMC water and sewage services are in progress. Detail Report
Graph / Photo
13 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). 2022.09.30 2023.03.29 818.33 SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
14 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi 2022.07.14 2022.10.13 751.50 Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
15 Strengthening of road of Bawana to Auchandi Border under Sub-Division NR-15, PWD Division North Roads, Delhi 2022.04.28 2022.10.24 718.31 761.73 (Oct'22) 0.00 (Oct'22) SBG Infracon Pvt Ltd Detail Report
Graph / Photo
16 Strengthening of Outer Ring Road from Wazirabad Flyover to Gandhi Vihar Subway under Sub Division-1, Division C&ND-Road, PWD, New Delhi. 2022.06.24 2022.08.23 717.68 473.42 (Oct'22) 0.00 (Oct'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
17 Laying of RCC Drain/pipe and raising of levels of existing carriage way of Ring Road in between toe of IP Flyover and opposite of WHO Building including laying of 1200mm dia. Pipe through trenchless pushing to solve water logging problem, New Delhi. 2022.04.28 2022.07.11 694.86 509.48 (Aug'22) 0.00 (Aug'22) A S INFRATECH Detail Report
Graph / Photo
18 Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi 2022.04.28 2022.10.24 643.92 103.55 (Oct'22) 0.00 (Oct'22) Kundu Nirma Detail Report
Graph / Photo
19 Strengthening of roads from Nangli Poona to Mohan Adda, Khera Kalan Road, Safiabad Mor to Safiabad Border, Holambi Kalan Crossing to Bawana Narela Road via Metro Vihar, under Sub-Division NR-13 of North Road Division, PWD, Delhi 2022.03.20 2022.07.17 640.59 574.70 (Oct'22) 0.00 (Oct'22) SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
20 Resurfacing of roads from (i) Lampur Mor to Lampur Border, (ii) Ramdev Chowk to Railway crossing Narela, (iii) Y-section Narela to Shahpur Garhi Turn, under Sub-Division NR-13, North Roads Division, PWD, Delhi 2022.03.20 2022.07.17 617.72 171.52 (Aug'22) 0.00 (Aug'22) Sethi Construction Detail Report
Graph / Photo
21 Strengthening of Apeejay School Road Sheikh Sarai Phase-1 Road no.1 and Road no.-2 Khirki Road Birla Vidya Niketan Marg Mandir Marg Main Road Sector-1 Pushp Vihar Pankaj Juyal Marg H-Block Road and NBCC Plaza Road under sub division SR-14. 2019.11.15 2020.05.14 615.93 841.57 (Sep'22) 0.00 (Sep'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
22 Strengthening of Road No. 56 i.c Service Road from Gazipur Grade Separator to Apsara Border and its subsequent maintenance for three years. 2021.11.27 2022.03.26 615.26 574.18 (Oct'22) 0.00 (Oct'22) Pawan Kumar Detail Report
Graph / Photo
23 Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW 2022.02.27 2022.06.26 548.07 265.84 (Oct'22) 0.00 (Oct'22) RK Brothers Detail Report
Graph / Photo
24 Strengthening of Arterial Roads having right of way more than 30.00 metre like Satyagrah Marg, IG Slip Road, Velodrome Road, Sachivalya Road, Club Road & Flag Staff Road under Sub Division – 3 of Division C & ND – Roads, New Delhi 2022.03.31 2022.06.30 535.88 469.00 (Jun'22) 0.00 (Jun'22) A S INFRATECH Detail Report
Graph / Photo
25 Resurfacing of roads from (i) Shahpur Garhi Turn to Old GTK road Alipur, (ii) Shubhash Chowk to Palla Village via Bakhtawarpur, (iii) Holambi Khurd Crossing to Shahpur Garhi turn, (iv) New GTK Road to Old GTK Road (via Shani Mandir), (v) New GTK Road to Old GTK Road (via PHC Alipur) under Sub-Division NR13, PWD North Roads Division, Delhi. 2022.03.20 2022.07.17 526.50 528.46 (Aug'22) 0.00 (Aug'22) SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
26 Strengthening of Swaroop Nagar Road with Construction of footpath on existing drain and improvement of road side berm from Main Burari Road to Kathia Baba Ashram under Sub Division-1, C&ND-Road Division Delh 2022.04.28 2022.06.27 523.21 200.00 (Oct'22) 0.00 (Oct'22) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
27 Construction of Two No. Foot Over Bridge across Sri Aurobindo Marg (ID-96) at (i) PTS Bus Stop (ii) T.B. Hospital with staircase and lift including Electrical Installations under Sub Division-II of Division South Road-II, PWD New Delhi. 2020.03.21 2020.09.20 489.85 203.60 (Jun'22) 0.00 (Jun'22) S S Chauhan & Sons Work in Progress. Detail Report
Graph / Photo
28 Widening and Strengthening of Bandh Road of Division SR-1 under Sub-Division SR-13 at New Delhi i/c shifting and installation of Electrical Poles Street lights etc. 2019.12.01 2020.05.31 459.03 354.65 (Jul'22) 0.00 (Jul'22) Bansal Associates Detail Report
Graph / Photo
29 Construction of precast drain and Improvement of side berm including footpath from Amrit Vihar to Nathupura road on Main Burari Road 2022.04.28 2022.07.12 434.22 245.90 (Oct'22) 0.00 (Oct'22) Amit Buildcon Detail Report
Graph / Photo
30 Remodeling of Maujpur drain from Road No. 66 to Ghonda Chowk and Main Brahmpuri Road drain from Ghonda Chowk to MCD Dhalav. 2018.10.28 2019.04.27 419.30 324.29 (Feb'22) 0.00 (Feb'22) Gee International work in progress Detail Report
Graph / Photo
31 Construction of RCC drain in Narela Alipur road along the DDA land from Bhorgarh to Shahpur Garhi turn under Sub Division NR-13, North Roads Division,PWD, Delhi 2022.01.07 2022.07.05 412.34 111.83 (Jun'22) 0.00 (Jun'22) R K Enterprises Detail Report
Graph / Photo
32 Thermoplastic painting on various roads under Division M-413, New Delhi dg. 2013-14. 2013.10.29 2014.02.28 404.14 K.L. Arora & Son Detail Report
Graph / Photo
33 Strengthening of various roads by cold milling and recycling process of Sub. Division East Road-II under Division East Road/(M-212), Delhi during 2022-23:- 1. NH-24 Ghazipur to Kondli Bridge. 2. Sameer Bhan Marg. 3. Road from Live stock market to Gali No. 7 Block - C in Ghazipur Dairy Farm. 4. Bhagvan Mahavir Swami Marg. 5. Road from High land Apptt. To Soochna Apptt. In Vasundhara Enclave 2022.08.29 2022.12.26 389.08 SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
34 Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain 2022.09.25 2022.12.24 386.35 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
35 Improvement of Khari Bawali and HC Sen Marg 2013.09.27 2015.05.26 382.36 Satya Parkash & Bros. Pvt. Ltd. Detail Report
Graph / Photo
36 Strengthening of Geeta Colony Yamuna Bridge Road from Ring Road Crossing to Pusta Road by cold milling and recycling process. Sub-Division East Road-I under Division East Road/(M-212) Delhi. dg. 2021-22 2022.02.25 2022.05.25 362.56 430.06 (Sep'22) 0.00 (Sep'22) Pawan Kumar Detail Report
Graph / Photo
37 Construction of Foot Over Bridge at Gurudwara Majnu ka Tila on Road No. 45 under Sub-Division-4 of Division C and ND-R, New Delhi. 2022.09.06 2023.03.05 358.46 Fiberfill Engineer Detail Report
Graph / Photo
38 Strengthening of various roads under Sub Division SR-11/South Road-1 PWD New Delhi.Phirni Road West End Marg Durbal Nath Marg H Block Dakshin Puri Road Maharishi Balmiki Marg and Raja Ram Marg. 2019.11.06 2020.02.05 348.51 461.79 (Jul'22) 0.00 (Jul'22) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
39 Strengthening of various roads by cold milling of sub-Div. East road-III under East road/(M-212) Delhi during 2022-23. 1. Sadhabhawna Marg (Road No. 111) 2. Club Avenue Marg (Road No. 112) 3. Sekarita Marg (Road No. 113) 4. Ambedkar Marg. 5. Subhash Market road. 6. Block No. 1 to 11 Trilokpuri. 7. Khudiram Bose Marg 2022.08.29 2023.02.24 342.13 SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
40 Strengthening of Dera Bhatti Road of Sub-Division SR-13 under Division SR-1 at New Delhi. 2019.11.27 2020.02.26 341.72 501.17 (Mar'22) 0.00 (Mar'22) Bansal Associates Detail Report
Graph / Photo
41 Strengthening of Western Approaches of Signature Bridge from Signature Bridge to Majnu ka Tila, Signature Bridge to Timarpur, Azadpur and Slip road from Wazirabad flyover to Signature Bridge, Burari flyover and Tagore Park under Sub Division-1, C&ND-Roads, New Delhi 2022.03.31 2022.06.30 336.11 484.99 (Jul'22) 0.00 (Jul'22) SATYA PARKASH AND BROS PVT LTD Detail Report
Graph / Photo
42 Construction of drains, footpath Central Verge and improvement of side berm portion of S-Bend road (Maharishi Dayanand Marg ID-539) New Delhi. 2019.10.24 2020.01.23 330.83 376.66 (Jul'22) 0.00 (Jul'22) S S Chauhan & Sons Work in Progress Detail Report
Graph / Photo
43 Comprehensive Maintenance of various Roads under SRD Project Division-I, Sub-Division-I, PWD, Delhi. (SH- Civil Works- Mechanised Desilting of Drains, Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other misc. Repair wor 2019.08.27 2020.08.23 323.91 485.41 (May'21) 0.00 (May'21) Awasthi Construcion Co. Detail Report
Graph / Photo
44 Remodelling of drain from 5th Pusta to Ghonda Chowk at Gamri Road Delhi 2020.01.13 2020.04.05 318.40 352.26 (Sep'22) 0.00 (Sep'22) Thermal Enginners & Insulators Pvt. Ltd. Detail Report
Graph / Photo
45 Strengthening of Mall Road from Timarpur Red Light to GTB Metro Station under Sub-Division-2 of Division C& ND-Roads, New Delhi. (Width- ROW Above 60.00 meter). 2022.04.28 2022.06.27 302.96 382.19 (Aug'22) 0.00 (Aug'22) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
46 Resurfacing of Road and Repairing of footpath and Central Verge at Asaf Ali Road and Chaman Lal Marg under Division SRD Project I, under Sub Division II, PWD during 2019 20 New Delhi 2019.09.23 2020.03.20 302.16 285.99 (Dec'21) 0.00 (Dec'21) Chaudhary Construction Company Pvt. Ltd. Detail Report
Graph / Photo
47 Providing and fixing M.S Steel railing at central verge of SSN Marg. 2019.11.03 2020.05.02 295.66 394.81 (Oct'22) 0.00 (Oct'22) B M & Sons Detail Report
Graph / Photo
48 Strengthening of Arterial Road (Bahadur Shah Zafar Marg) having right of way more than 60.00 metre under Sub Division – 3 of Division C & ND – Roads, New Delhi 2022.03.31 2022.05.30 289.31 260.08 (Sep'22) 0.00 (Sep'22) A S INFRATECH Detail Report
Graph / Photo
49 Comprehensive Maintenance of Aacharya Shree Tulsi Marg M.G.Road Aya Nagar Road Ghitorni Road to CPWD Land Ghitorni Village Road M.G.Road to Ghitorni Village Road and Mandi Road under the Jurisdiction SD-15 under SR-1 during 2019-20 2019.11.01 2020.10.31 288.88 426.77 (Jan'22) 0.00 (Jan'22) S S Chauhan & Sons Detail Report
Graph / Photo
50 Comprehensive Maintenance of various Roads under SRD Project Division-I, Sub-Division-II, PWD, Delhi. (SH- Civil Works- Mechanised Desilting of Drains, Mechanised Repairing of Pot Holes, Maintenance and Cleaning of Subways and other misc. Repair wo 2019.08.24 2020.08.23 285.85 569.67 (Aug'21) 0.00 (Aug'21) Awasthi Construcion Co. Detail Report
Graph / Photo
51 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub Division-1, C&ND-Road Division. 2nd RECALL 2022.07.20 2022.11.19 243.86 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
52 Widening of IGNOU Road and construction of RCC drain and footpath at IGNOU Road from Z more to M.B. Road T-Point. 2018.07.18 2018.09.16 242.58 392.31 (Aug'21) 0.00 (Aug'21) Y. D. Builders & Hotel Pvt Ltd Work in progress Detail Report
Graph / Photo
53 Widening of road and providing road infrastructure near Majnu ka Tila and Chandgi Ram Akhara for implementation of back-to-back U-turn under Sub. Division-1, C and ND-Road Division. (1st RECALL) 2022.03.09 2022.07.08 225.35 Sethi Construction Detail Report
Graph / Photo
54 Construction of Foot Over Bridge with staircase, electrical works and lift for pedestrian across press Enclave Road near Select City Mall, New Delhi. 2019.08.31 2020.02.29 222.53 187.92 (Jul'20) 0.00 (Jul'20) S. S. Chauhan & Sons Detail Report
Graph / Photo
55 Improvement of riding surface of flyovers namely Nand Nagri flyover, Loni Flyover, Gokalpuri and Khajuri Gol Chakkar Flyover on Wazirabad Road (Road No- 63 and 59) 2019.07.15 2019.10.14 192.33 245.19 (Dec'21) 0.00 (Dec'21) Pawan Kumar Work in progress. Detail Report
Graph / Photo
56 Improvement of Sewadham Road from road No.-63 to UP Border. 2019.03.01 2019.04.30 190.73 226.00 (Jul'19) 0.00 (Jul'19) Pawan Kumar work in progress Detail Report
Graph / Photo
57 Strengthening of (1) Rishabh Vihar Road, (2) Surajmal Vihar Market Road and (3) Shrestha Vihar Road, under Sub-Division M-2112 during 2021-22. (Modified 2nd recall) 2022.03.18 2022.05.16 153.67 188.95 (Oct'22) 0.00 (Oct'22) Nirmit Construction Co. Detail Report
Graph / Photo
58 Providing and laying waste water pipe line from Arvind Nagar pump house Gamri Road to Drain no. 1 at road no. 66 via Maujpur Road Delhi. 2019.02.26 2019.06.25 149.77 182.60 (Nov'20) 0.00 (Nov'20) K. CONSTRUCTION COMPANY work in progress Detail Report
Graph / Photo
59 Upgradation of 21 Nos. staff rooms of GNCTD Schools under Jurisdiction of SRD Project Division-1, PWD dg. 2018-19 2018.11.30 2019.01.28 135.88 147.99 (Feb'21) 0.00 (Feb'21) Munzareen Ahmed work in progress Detail Report
Graph / Photo
60 Construction of RCC drain at Budh Ram Singh Marg and Sameer Bhan Marg 2018.12.08 2019.03.07 130.52 63.31 (Sep'21) 0.00 (Sep'21) Dinesh Chand Sharma

Work in progress

Detail Report
Graph / Photo
61 Construction of Foot Over Bridge balance portion at D.B. Gupta Road 2014.08.28 2014.12.27 129.06 K.L. Arora & Son Detail Report
Graph / Photo
62 Strengthening of Roshnara Road by cold milling method from Pulbangash Metro Station to Roshnara Gol Chakkar 2022.03.31 2022.05.30 124.78 297.30 (Apr'22) 0.00 (Apr'22) A S INFRATECH Detail Report
Graph / Photo
63 Redevelopment of drainage system at Lothian SPM Road Junction and Construction of Sump. (SH Civil Works) 2018.09.28 2019.01.25 122.76 122.76 (Jan'22) 0.00 (Jan'22) K.P. Singh & Co. Work in progress Detail Report
Graph / Photo
64 Strengthening of Gandhi Vihar Main Road under jurisdiction of Sub Division-1, C and ND-Road Division Delhi 2022.03.31 2022.05.30 122.01 193.12 (Oct'22) 0.00 (Oct'22) A S INFRATECH Detail Report
Graph / Photo
65 Microsurfacing on carriageway of Main Burari Road from Nathupura to Hiranki and All University Campus under Sub. Division-1 of Division C and ND-R during the year 2021-22 2022.04.07 2022.06.06 120.44 M C Constructions Company Detail Report
Graph / Photo
66 Construction of Foot Over Bridge near Kardampuri and Yamuna Vihar on Road No.-66 , Delhi (Approximate Length 30.00 Metre). 2019.06.09 2019.09.06 98.85 146.98 (Dec'21) 0.00 (Dec'21) Dilshad Khan Work in progress. Detail Report
Graph / Photo
67 Resurfacing of Sadar Thana Road, Foota Road, Bahadur Garh Road, Chelmsford and Faiz Road. 2016.09.14 2017.01.13 88.85 18.77 (Apr'21) 0.00 (Apr'21) Raj Kumar Sachdeva Permission from the Traffic Police not received. Detail Report
Graph / Photo
68 Restoration of outer ring road (Keshopur Mandi to Janakpuri) cut by BSES for Laying of 04 Nos Cables under sub division WR-13, Division West Road-1 PWD during 2022-23 via ID 202112311521139. 2022.07.15 2022.08.28 82.92 MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
69 Construction of R.C.C. central verge on August Kranti Marg from Kotla Flyover to Siri Fort Red Light (ID-16) under Sub Division-I of Division South Road-2, PWD, Delhi during 2022-23 2022.05.31 2022.07.30 81.49 39.10 (Sep'22) 0.00 (Sep'22) Samridhi Construction Detail Report
Graph / Photo
70 Strengthening of road from Service Road Oberoi Flyover, Service Road ROB, Bhogal & School Road of Sub-Division R-14 under Division South East Road-1. 2022.07.02 2022.07.31 78.53 M C Constructions Company Detail Report
Graph / Photo
71 Providing and laying microsurfacing of B-4 road under Sub Division NWR-23, PWD Division NWR-2 during 2021-22 2022.05.30 2022.07.13 78.40 SBG Infracon Pvt Ltd Detail Report
Graph / Photo
72 Providing and laying microsurfacing of various roads (B-6 Road, Coln. Sarna Marg, N.K. Bagrodia School to Vinobha Kunj, Chetak Appt. to New Modern Appt., Vidya Vihar to Neelgiri Appt. and Pragatisheel Appt. to Green View Appt.under Sub Division NWR-23, PWD Division NWR-2 dg. 2022-23. 2022.09.09 2022.10.22 75.51 M.C. Construction Detail Report
Graph / Photo
73 Construction of RCC drain from NH-24 to Hindon cut at Murga Mandi Road, New Delhi 2022.02.14 2022.07.13 70.84 49.50 (May'22) 0.00 (May'22) Ravinder Kumar Detail Report
Graph / Photo
74 Providing and Laying Stone Matrix Asphalt on Tilak Nagar Flyover under Sub Division WR 13 2022.06.01 2022.08.29 70.74 82.65 (Sep'22) 0.00 (Sep'22) RK Brothers and Co Detail Report
Graph / Photo
75 Improvement and Strengthening of Gamri Road from 5th Pusta to Ghonda Chowk Delhi 2019.08.02 2019.10.29 69.82 69.55 (Jan'20) 0.00 (Jan'20) MAHAVIR PRASAD GUPTA AND SONS Work in Progress Detail Report
Graph / Photo
76 Restoration of Road cut by DJB at Abdul Aziz Road from Pusa road crossing to Bank Street, New Delhi 2016.12.23 2017.01.21 68.15 Bishwa Mohan Jha Determined Detail Report
Graph / Photo
77 Micro surfacing of various Road under SRD Project Sub-Division III SRD Project Division II PWD New Delhi SH Micro surfacing and Improvement of footpath at Arya Samaj Road 2018.08.20 2019.02.11 66.76 70.27 (Jan'21) 0.00 (Jan'21) SATYA PARKASH AND BROS PVT LTD Work in Progress Detail Report
Graph / Photo
78 Construction of Drain from I.P. Estate DTC Depot to SDMC Drain & Making Slip Road near New Railway Bridge at Ring Road between Bhairon Marg T-Junction and Entry Tunnel Ring Road under Division C&ND- Roads, New Delhi. 2022.04.25 2022.05.24 66.21 Gee Internationals Detail Report
Graph / Photo
79 Providing main LT panels, Distribution boards i/c providing LED fittings, Ceiling Fans, & replacement of Air Conditioners, DG set with suitable AMF panel and other miscellaneous electrical work for Department of Training & Technical Building at Muni Maya Ram Marg, Pitampura, Delhi 2022.04.08 2022.10.07 64.45 30.41 (Oct'22) 0.00 (Oct'22) M/s R S Electric Co. Detail Report
Graph / Photo
80 A/R and M/O Various Roads under Project Circle, PWD, New Delhi dg. 2017-18 (SH-Security Guards for various offices under Project Circle, PWD, Govt, of Delhi). 2017.06.29 2018.06.28 63.56 0.00 (Mar'19) 77.10 % (Mar'19) Good Year Security Services Work completed and final bill paid Detail Report
Graph / Photo
81 Resurfacing of Road under SRD Project Sub-Division III SRD Project Division II PWD New Delhi SH Resurfacing of road and improvement of Footpath at Tank Road 2018.08.18 2019.02.12 63.43 73.44 (Sep'19) 0.00 (Sep'19) RAJ KUMAR SACHDEVA Work completed Detail Report
Graph / Photo
82 A/R and M/O to various roads under SRD Project Division-I during 2018-19. (SH-Repairing of Drain andfootpath at back side of New Delhi court building at Kotla Road and repairing of footpath NMV Lane infront of Court building at DDU Marg under Sub Di 2018.06.21 2018.10.20 59.92 74.26 (Sep'19) 0.00 (Sep'19) Satyam Construction Co. work in progress Detail Report
Graph / Photo
83 Construction of RCC drain at Dallupura Road Near Timber Market 2018.12.13 2019.03.12 59.46 12.01 (Jan'21) 0.00 (Jan'21) Shiv Construction Co.

Work in progress

Detail Report
Graph / Photo
84 Restoration of various road under SRD Project Sub Divn. I SRD Project Divn. II PWD, New Delhi.SH Restoration of road cut by BSES at Panchkuiyan Road, Rani Jhansi Road and D.B. Gupta Road 2018.04.24 2018.07.22 58.00 AMCON Work completed Detail Report
Graph / Photo
85 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2016-17. SH Bituminous concrete patch repair. 2016.12.03 2017.03.02 56.05 Chaudhary Construction Co. Completed Detail Report
Graph / Photo
86 Widening of Bhagwan Pur Khera Culvert over 52 cusec drain on Loni Road. 2019.08.09 2019.12.06 55.71 62.33 (Dec'21) 0.00 (Dec'21) Ravinder Kumar award under process Detail Report
Graph / Photo
87 Desilting of drains by chassis mounted high pressure suction cum jetting machine under Sub Division 2. 2019.08.05 2019.10.04 55.58 51.12 (Dec'21) 0.00 (Dec'21) Maan Builders award in process Detail Report
Graph / Photo
88 Comprehensive Development of Corridor (Outer Ring Road) between Mukarba Chowk to Wazirabad. SH. Providing and laying stone pitching and chute drain on embankment slope and construction of cycle track. 2017.04.10 2017.04.09 55.56 AANISHA COMMUNICATION PVT.LTD. Detail Report
Graph / Photo
89 A/R and M/O to various roads under PWD (North East) Road Division dg. 2019-20. (SH- Providing M.S. Grill in central verge from Railway Line bridge to Road no. 66 T-Point at Road no. 68 under PWD Sub Division-4). 2019.08.18 2019.11.16 54.89 46.71 (Aug'20) 0.00 (Aug'20) MOHD. FIROZ Detail Report
Graph / Photo
90 AR Mo to various roads under PWD SWR II dg 2018 19 SH Improvement of Drain from Golak Dham to Bijwasan flyover RHS and providing footpath from IOC Morh to Bijwasan Flyover Sub Division 24 2019.03.22 2019.07.19 54.67 1.37 (May'22) 0.00 (May'22) Bishwa Mohan Jha work in progress Detail Report
Graph / Photo
91 Construction of Slip Road in front of Gurudwara Majnu Ka Tila at Road No. 45 under Sub. Division-1 of Division C&ND-Roads, New Delhi. 2nd CALL 2022.05.03 2022.08.02 54.58 Aditya Construction Detail Report
Graph / Photo
92 Micro surfacing of various Road under SRD Project Sub-Division III SRD Project Division II PWD New Delhi SH Micro surfacing and Improvement of footpath at East Park Road 2018.08.20 2019.02.12 54.25 53.03 (Nov'20) 0.00 (Nov'20) SATYA PARKASH AND BROS PVT LTD Work Completed & first R/A bill paid for Rs. 1777119 Detail Report
Graph / Photo
93 A/R and M/O to various road under SRD Project Sub-Division-III/SRD Project Division-II, PWD, New Delhi during 2017-18 SH Comprehensive Maintenance of road 2018.03.20 2018.11.14 52.96 Satyam Construction Co. Work Completed Detail Report
Graph / Photo
94 AR and Mo to various roads under Sub Division 21 SWR-II PWD dg 2018 19. SH Repair of drain and footpath on Peer Baba Road ID 1218 Bindapur New Delhi. 2019.02.11 2019.05.11 52.63 BLG Innovations work in progress Detail Report
Graph / Photo
95 Construction of Central Verge with R.C.C. crash barriers at Dharam Marg under Sub Division WR-11, Division WR-1 during 2022-23 2022.10.08 2022.12.06 52.49 Kulwant Singh Detail Report
Graph / Photo
96 Improvement of Central Verge on Road No. 66 from 1st Metro Pillar (Seelampur side) to Moujpur Chowk Red light. 2019.06.30 2019.07.29 52.35 65.96 (Dec'21) 0.00 (Dec'21) Ravinder Kumar Work in progress. Detail Report
Graph / Photo
97 Resurfacing of Road under SRD Project Sub-Division III SRD Project Division II PWD New Delhi SH Resurfacing of road and improvement of Footpath at Gurudwara Road 2018.08.17 2018.12.14 50.73 54.15 (Nov'19) 0.00 (Nov'19) ASLAM BUILDERS Work completed Detail Report
Graph / Photo
98 Cement concrete patch repair at East park road footpath, Panchkuyia NMV, Crimination Ground at Rani Jhansi Road, Military Road and Ajmal Khan Road repair 2017.01.04 2017.04.03 50.49 Shree Vishnu Steel Works Completed Detail Report
Graph / Photo
99 Road Restoration at Goyla Deenpur Road Road Cut by Delhi Jal Board under Sub Div24 SWR II New Delhi dg 2018 19 2019.04.25 2019.06.23 50.28 Dhanna Ram & Sons work completed Detail Report
Graph / Photo
100 Comprehensive maintenance of various roads under SRD Project Division-I, Sub Division-II PWD, New Delhi during 2019-20. (SH- Misc. Repair Work.) 2019.03.18 2020.03.17 48.71 42.68 (Mar'21) 0.00 (Mar'21) M/s. Satyam Construction work in progress Detail Report
Graph / Photo
101 Renovation of A Block, B Block and C Block at Urdu Academy, CPO Building, Kashmere Gate under SRD Division-I, Sub-Division-III, PWD, New Delhi. 2018.08.13 2019.01.12 47.47 5.34 (Aug'20) 0.00 (Aug'20) Kamal Construction Co. Work completed final bill yet to be paid Detail Report
Graph / Photo
102 Relayering of Damaged Internal Roads at Lawyer Chamber Blocks (D,E,F,G & H Block) including raising of manhole cover, laying of c.c pavement at Karkardooma Court, Sahadara, Delhi-110032. 2022.05.26 2022.07.24 46.59 Uday Raj Pandey Detail Report
Graph / Photo
103 Resurfacing of Road under SRD Project Sub-Division III SRD Project Division II PWD New Delhi SH Resurfacing of Road and improvement of Footpath at Abdul Rehman Road 2018.08.18 2019.02.12 46.36 41.09 (Sep'19) 0.00 (Sep'19) RAJ KUMAR SACHDEVA Work completed Detail Report
Graph / Photo
104 Construction of RCC drain in front of Qutub Minar Metro Station from 100 foota road to culvert on Anuvrat Marg (ID-1198) under Sub Division -III of Division South Road-II, PWD, New Delhi during 2021-22 2022.03.18 2022.06.17 46.27 AMOCON Detail Report
Graph / Photo
105 Providing and fixing of Automation system of rainy water pumps installed at various under passes of Sub Division M-3513 Sindhora Kalan Delhi under the head, improvement of PWD roads (5054) 2022.05.07 2022.07.06 45.10 47.65 (Aug'22) 0.00 (Aug'22) B.D. Electrocom Pvt. Ltd. Detail Report
Graph / Photo
106 Providing and Fixing M.S. Railings on loni Road from Durgapuri chowk to Loni Gole chakkar under (North East) Road Division. 2019.06.30 2019.07.29 43.93 54.01 (Dec'21) 0.00 (Dec'21) Sandeep Kumar Work in progress. Detail Report
Graph / Photo
107 A/R and M/O various roads under SRD Division-I, Sub-Division-II, PWD, New Delhi dg. 2018-19. (SH-Repair/renovation of footpath/carriageway of Kotla road.) 2018.10.05 2018.11.19 43.03 15.05 (Oct'22) 0.00 (Oct'22) A.R Infrastructure Work in progress Detail Report
Graph / Photo
108 AR MO to various roads under Sub Div 21 Division SWR II PWD dg 2018 19 SH Repair of Footpath Misc Works at Satguru Ram Singh Marg New Delhi. 2019.03.12 2019.05.10 42.74 P. R. S. Yash & Co. work completed Detail Report
Graph / Photo
109 Road restoration work of road cutting done by DJB on Outer Ring Road and by BSES, MTNL, IGL, TATA, DJB on other various roads under sub division WR-13 2022.04.08 2022.08.05 42.06 50.13 (Sep'22) 0.00 (Sep'22) MAHAVIR PRASAD GUPTA AND SONS Detail Report
Graph / Photo
110 A/R and M/O to various roads under SRD Division-I, Sub-Division-II ,PWD, New Delhi during 18-19 (SH-Repairing of damaged portion of roads, under Matia Mahal Constituency) 2018.09.20 2018.11.19 39.91 Satyam Construction Company work completed final bill paid Detail Report
Graph / Photo
111 Raising of Existing RCC drain walls of big drain with provision of inspection chambers at Mukarba Chowk under Sub-Division NR-14, NorthRoad Division, PWD, Delhi (Balance work) 2022.05.14 2022.06.13 39.05 22.21 (Jul'22) 0.00 (Jul'22) Nurul Hak Detail Report
Graph / Photo
112 AR and Mo to various roads under PWD Division South West Road II New Delhi during 2019-20 SH Providing services of Clerk Computer Operators and MTS for Division Office 2019.08.01 2020.07.30 38.51 15.79 (Aug'20) 0.00 (Aug'20) M/s Trendy Security Services WORK IN PROGRESS Detail Report
Graph / Photo
113 Development of Khajuri Chowk for making left turn free of smooth flow of traffic under PWD Sub Division M-2134. 2019.12.31 2020.03.29 38.44 46.40 (Sep'22) 0.00 (Sep'22) Maan Builders Detail Report
Graph / Photo
114 AR and MO various roads under Project Circle PWD New Delhi during 2019 20 SH Security Guards for various offices under Project Circle SRD Project Division I and Sub Division I II and III 2019.09.29 2020.09.28 37.87 73.61 (Jan'22) 0.00 (Jan'22) Star security & Placement Services Detail Report
Graph / Photo
115 Providing and Placing Jersey type barrier at Captain javed Ali Marg and Road No.70 under sub div M-2114, New Delhi dg 2021-22. (Modified and IInd Call) 2022.05.22 2022.07.20 37.79 43.51 (Sep'22) 0.00 (Sep'22) M. T. Builders Detail Report
Graph / Photo
116 Provision for Rain Water Harvesting Systems in SKV Bulbuli Khana Matia Mahal, SBV No. 1 (UM) Jama Masjid and GGSSS Pataudi House Darya Ganj under SRD Project Division-I, Sub-Division-III, PWD, Delhi. 2018.11.09 2019.01.08 37.49 36.01 (Nov'20) 0.00 (Nov'20) Ved Pal work in progress Detail Report
Graph / Photo
117 Restoration of various road under SRD Project Sub Divn.III SRD Project Divn.II, PWD, New Delhi. SH Restoration of various road cut by BSES at D.B. Gupta Road, East Park Road, Sant Sujan Singh Road and Ajmal Khan Road. 2018.04.26 2018.06.23 36.92 AMOCON Work completed Detail Report
Graph / Photo
118 Road Restoration on various roads under Sub Division NWR-22, Division NWR-2, PWD, Delhi dg. 2022-23 2022.06.13 2022.12.09 36.66 28.19 (Oct'22) 0.00 (Oct'22) Jitender Singh Detail Report
Graph / Photo
119 AR and MO various roads under Division SWR-II, PWD Delhi during 2019-20. SH Improvement of drain by laying 600 mm dia NP3 pipe Hospital and BSES side from Rawta Morh to Jafferpur Engineering College in Prithvi Singh Dagar Marg 2019.09.03 2019.12.01 36.30 Ashok Kumar Rathi work not started Detail Report
Graph / Photo
120 Modification of berm portion at various roads in Sultanpuri Majra under Sub-Division NWR-21, Division NWR-2, New Delhi 2022.09.04 2022.11.03 36.09 Jitendra Singh Detail Report
Graph / Photo
121 Development of Open Land as Public Park at Sheikh Sarai - 2 Press Enclave Road New Delhi dg.2018-19. 2018.09.14 2018.12.12 35.74 51.72 (Sep'21) 0.00 (Sep'21) Ravi Tanwar Work in progress Detail Report
Graph / Photo
122 Uplifting of Central Verge on Main Road from Cambridge School to CTC at Sri Niwas Puri under Sub Div. R- 11 of Division South East Road -1. 2022.07.06 2022.10.03 35.65 AMOCON Detail Report
Graph / Photo
123 AR Mo various roads under PWD Division SWR II during 2018 19 SH Miscellaneous Repair work of drain path of Section II under Sub Division II New Delhi. 2019.03.12 2019.07.09 35.27 H.P Builders Pvt Ltd WORK foreclosed Detail Report
Graph / Photo
124 Providing and Placing Jersey type barrier at Captain javed Ali Marg and Road No.70 under sub div M-2114, New Delhi dg 2021-22. (Modified and 1st Call) 2022.03.20 2022.05.18 35.11 Anmol Infratech Private Limited Detail Report
Graph / Photo
125 Providing and Placing Jersey type barrier at Captain javed Ali Marg and Road No.70 under sub div M-2114, New Delhi dg 2021-22 2021.12.09 2022.02.06 34.31 Sirohi Construction Co Detail Report
Graph / Photo
126 Resurfacing of Road under SRD Project Sub Division-III SRD Project Division-II PWD New Delhi Sh Resurfacing of road and improvement of footpath at Elahi Bux Road 2018.08.17 2018.12.14 34.08 28.82 (Nov'19) 0.00 (Nov'19) ASLAM BUILDERS Work completed Detail Report
Graph / Photo
127 AR and Mo various roads under Division South West Road II PWD dg 2018-19 SH Providing and Installation of Sewerage Pump at Different Vulnerable Location under Sub Division III. 2019.02.07 2020.02.02 33.55 24.99 (Aug'19) 0.00 (Aug'19) Tripurari Prasad Singh work complted Detail Report
Graph / Photo
128 Improvement of Multi Model integration System at Welcome, East Azad Nagar, and Krishna Nagar Metro station under M-2111 dg. 2021-22. (IInd Call) 2022.05.14 2022.07.12 33.51 Avtar Builders Detail Report
Graph / Photo
129 A/R & M/O to various roads under M-4423 during 2014-15 (SH: Repair to storm water drain at IGNOU Road from MB Road cut to Z-crossing under Sub-Division M-4423). 2015.01.19 2015.03.18 32.55 Surender Singh Chouhan work completed Detail Report
Graph / Photo
130 Providing and fixing precast Jersey Barrier on Sadar Thana Road and Foota Road. 2017.01.25 2017.02.23 30.95 B.M. & Sons Completed Detail Report
Graph / Photo
131 Restoration of Road No. 5 from D.B. Gupta Road to Tank Road in Karol Bagh, New Delhi cut by Delhi Jal Board for laying sewer line 2017.01.01 2017.03.01 27.68 Aslam Builders Completed Detail Report
Graph / Photo
132 Improvement of Inner roads of Shiva Apartment at Road No.30, Paschim Vihar, Delhi. (Balance Work) 2022.05.16 2022.08.15 27.54 18.56 (Sep'22) 0.00 (Sep'22) Jitender Singh Detail Report
Graph / Photo
133 Renovation work in Kothi No. 3, Behind DCP Office Complex, Central Distt. Darya Ganj, under SRD Division-I, Sub-Division-III, PWD, New Delhi-110002. 2018.06.02 2018.11.01 27.48 34.29 (Jun'19) 0.00 (Jun'19) Manohar Lal Sharma Work in porgress Detail Report
Graph / Photo
134 Remodeling of Drain on Road No. 236 towards Samaj Kalyan Society under Sub Division WR-14 Division WR-1 during 2021-22.(Revised) 2022.04.22 2022.06.20 26.90 Jeetender Kumar Verma Detail Report
Graph / Photo
135 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2016-17. SH Desilting of Road side storm water Drains. 2017.05.03 2017.07.31 26.32 Shakur Ahmed & Sons Completed Detail Report
Graph / Photo
136 A/R and M/O various road under PWD SRD Project Division-I, PWD, New Delhi dg. 2018-19. (SH-Provision of two nos. yellow coloured maintenance van with required labour and T and P for day to day maintenance of roads). 2018.11.26 2019.11.25 25.46 12.62 (Oct'19) 0.00 (Oct'19) RANJIT CONSTRUCTION COMPANY work in progress Detail Report
Graph / Photo
137 A/R and M/O various Roads under SRD Project Sub-Division-III/SRD Project Division-II, PWD, New Delhi during 2017-18. 2017.11.22 2018.01.05 24.68 Shiv Shakti Enterprises DETERMINED Detail Report
Graph / Photo
138 AR and Mo various roads under Division South West Road II PWD dg 2018 19 SH Providing of Maintenance Van with required labours T and P for day to day upkeeping maintenance of roads under Sub Div III Jaffarpur Section. 2019.02.13 2020.02.12 24.14 23.98 (May'22) 0.00 (May'22) Bishwa Mohan Jha work in progress Detail Report
Graph / Photo
139 Improvement of various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2016-17. SH: Footpath repair in Panchkuiyan Road, Rani Jhansi Road and New Rohtak Road, Karol Bagh. 2017.05.22 2017.07.20 23.85 Ramesh Chand Completed Detail Report
Graph / Photo
140 A/R & M/O to various Roads under SRD Project Division-II, New Delhi dg. 2017-18. SH: Monsoon preparation works. 2017.05.31 2017.09.27 22.46 Kashi Nath Jha completed Detail Report
Graph / Photo
141 Restoration of road under SRD Project Sub Division III SRD Project DivisionII, PWD, New Delhi during 2017-18.SH Restoration of various road cut by BSES at DB Gupta Road Ajmal Khan Road Saraswati Marg, Vishnu Mandir Marg and Padam Singh Road. 2018.04.24 2018.06.07 21.61 Satyam Construction Co. Work completed Detail Report
Graph / Photo
142 A/R and M/O various roads under SRD Division, PWD, New Delhi, During 2018-19. (SH-Desilting of road side water drain/ sewer line by manual and super sucker machine on Various roads, under Sub Division-II.) 2019.03.10 2019.09.09 20.87 33.58 (Aug'20) 0.00 (Aug'20) M/s. Satyam Construction work in progress Detail Report
Graph / Photo
143 Construction of Footpath and other relevant work in Shahdara Road and Bholanath Nagar Road under sub division M-2113 Delhi. 2022.06.19 2022.08.17 20.73 Ram Kirpal Singh Detail Report
Graph / Photo
144 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18 SH Repair of footpath and central verge on Azad Market Road 2018.02.07 2018.04.07 20.54 Kashi Nath Jha Work Completed Detail Report
Graph / Photo
145 Construction of RCC drain under Sub Division M-2112 during 2022-23. (SH:- Remodeling of drain B-Block Vivek vihar Near DDA Market and Vivek Vihar Pump House). 2022.05.15 2022.08.12 20.16 18.71 (Aug'22) 0.00 (Aug'22) BASAU CONSTRUCTION (INDIA) Detail Report
Graph / Photo
146 A/R and M/O other PWD roads under SRD Division-I, Sub-Division-I, PWD, New Delhi dg. 2018-19 (SH-Repairing of footpath and other Misc. work at Gokhle Road) 2019.03.18 2019.07.17 19.92 24.81 (Nov'19) 0.00 (Nov'19) TKN Developers work in progress Detail Report
Graph / Photo
147 A/R and M/O to various roads under SRD Project Division-I during 2016-17 (SH-Laying of storm water pipe and reconstruction of footpath near Gurudwara side gate to Mata Sundri College on Mata Sundri Road Kotla Road around Gurudwara). 2017.06.02 2017.09.01 19.82 0.00 (Mar'18) 24.61 % (Mar'18) Satyam Construction Company Detail Report
Graph / Photo
148 Construction of Culverts and missing drain at Tanga Stand Road under Sub Division M2114, New Delhi during 2022-23. 2022.09.23 2022.11.21 19.76 Praveen Kumar Detail Report
Graph / Photo
149 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Development of Baba Lal Dayal Chowk. 2017.12.29 2018.02.11 19.68 Sirohi Construction Co. Work Completed Detail Report
Graph / Photo
150 Remodeling of Culvert from Sai Chowk to Radha Krishna Mandir under Sub Div. M-2114 dg. 2021-22 2022.03.19 2022.06.16 19.68 25.81 (Jul'22) 0.00 (Jul'22) Anish Verma Detail Report
Graph / Photo
151 A/R and M/O various roads under SRD Division-I, Sub-Division-II, PWD, New Delhi during 2018-19. (SH- Repairing of damaged Footpath, Central Verge and Main Carriageway at Asaf Ali Road.) 2019.03.18 2019.06.17 19.62 24.40 (Nov'19) 0.00 (Nov'19) M/s. Satyam Construction work in progress Detail Report
Graph / Photo
152 A/R and M/O various Roads under SRD Project Sub-Division-III/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Repair of Footpath at Guru Dwara Road, Abdul Aziz Road, Ganga Mandir Marg and Desh Bandhu Gupta Road etc 2017.12.29 2018.03.28 19.45 Sirohi Construction Co. Work Completed Detail Report
Graph / Photo
153 Road Restoration of various roads cut by TPDDL, BSES, Airtel, Jio and DJB under Sub Division NWR-24 (Section-II), PWD Division NWR-2 dg. 2021-22. (Re-call) 2022.05.02 2022.06.15 19.26 24.66 (Sep'22) 0.00 (Sep'22) J.S. Construction Co. Detail Report
Graph / Photo
154 A/R and M/O various roads under SRD Division, PWD, New Delhi, During 2018-19. (SH-Desilting of road side water drain/ sewer line by manual and super sucker machine on Various roads, under Sub Division-I.) 2019.03.10 2019.09.09 18.54 23.10 (Mar'20) 0.00 (Mar'20) Shiva Construction work in progress Detail Report
Graph / Photo
155 A/R & M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2016-17. SH: Provision of Maintenance Van in Karol Bagh (Roads in between D.B Gupta Road & New Rohtak Road from Faiz Road crossing to Military Road and Arya Samaj Road). 2016.12.19 2017.09.14 18.25 AMCON Completed Detail Report
Graph / Photo
156 A/R and M/O various roads under SRD Division-I, Sub-Division-II, PWD, New Delhi during 2018-19. (SH- Repairing of damaged Footpath, NMV Lanes and Planters in front of LNJP Hospital at JLN Marg) 2019.03.18 2019.06.17 17.56 21.01 (Jan'20) 0.00 (Jan'20) M/s. Satyam Construction work in progress Detail Report
Graph / Photo
157 A/R and M/O to other PWD roads under SRD Division-I, New Delhi dg. 2018-19 (SH- Repairing of footpath and other Misc. work at Zorawar Singh Marg under Sub Division-I) 2019.02.26 2019.03.25 17.56 21.83 (Sep'19) 0.00 (Sep'19) Sirohi Construction Co work in progress Detail Report
Graph / Photo
158 A/R and M/O to various roads under SRD Division-I, PWD, New Delhi dg. 2018-19. (SH-Repairing of Traffic Islands at Jawahar Lal Nehru Marg and Turkman Road.) 2018.12.02 2019.02.01 17.49 0.00 (Mar'19) 21.43 % (Mar'19) M/s. Satyam Construction Work completed final bill paid Detail Report
Graph / Photo
159 Renovation of office of Commission for Protection of Child Rights, GNCT Delhi in ISBT Building Kashmere Gate under SRD Division-I, Sub-Division-III, PWD, New Delhi. 2019.02.26 2019.05.25 17.37 12.48 (Feb'20) 0.00 (Feb'20) SUDHIR KUMAR SHARMA work in progress Detail Report
Graph / Photo
160 P/L RMC at deepressed berm portions and laying of kerb stone at centre verge of Vedic Marg 2022.04.28 2022.06.26 17.13 SHRI KRISHNA CONSTRUCTION COMPANY Detail Report
Graph / Photo
161 AR Mo various roads under Division South West Road II PWD dg 2018 19 SH Supply of Material for day to day Maintenance of Roads under Sub Division 21 New Delhi. 2019.03.15 2019.07.12 17.02 ASH NARAYAN SINGH work complete Detail Report
Graph / Photo
162 A/R and M/O various roads under SRD Project Division-I, Sub-Division-II, PWD, New Delhi during 2018-19. (SH-Improvement of footpath, drainage and main carriageway at Mirdard Road.) 2019.03.18 2019.06.17 16.55 20.33 (Nov'19) 0.00 (Nov'19) M/s. Satyam Construction work in progress Detail Report
Graph / Photo
163 Providing and laying of M.S. pipe line with sump and pump house near Sanjay Enclave Mall Road Extension (Mukarba Chowk), Jahangirpuri for disposal of excessive water under Sub Division NR-12 2022.03.25 2022.04.23 16.16 18.63 (Oct'22) 0.00 (Oct'22) Sanjay Kaura Detail Report
Graph / Photo
164 Construction of new planters from Vidya Vihar to Police Line at ORR-26 and C/o brick drain near B-Block Mangolpuri Delhi under Sub Division NWR-25, PWD Division NWR-2 dg. 2022-23. 2022.07.16 2022.09.15 14.96 7.08 (Oct'22) 0.00 (Oct'22) Sanjay Kaura Detail Report
Graph / Photo
165 A/R and M/O to various road under PWD SRD Project Division-I, dg. 2017-18 (SH-Provision of yellow coloured two maintenance van with required labour with T and P to attend day to day maintenance under Sub Division-II). 2017.06.25 2017.12.24 14.94 0.00 (Mar'18) 18.63 % (Mar'18) Satyam Construction Company Work completed and final bill paid Detail Report
Graph / Photo
166 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Misc. Road Repair works under Sadar Constituency) 2018.02.06 2018.05.07 14.88 TKN Developers Work Completed Detail Report
Graph / Photo
167 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Laying of non pressure NP-2 class (light duty) R.C.C. pipes on Pahari Dhiraj road.) 2018.03.05 2018.05.03 14.77 Surender Singh Chahal Foreclosed on 18.12.2018 Detail Report
Graph / Photo
168 Construction of footpath at road from Chetak Appt. to New modern Appt. Rohini, Sector-2 under PWD Division NWR-2, Sub Division NWR-23 during 2021-22 2022.04.27 2022.06.26 14.13 16.96 (Jul'22) 0.00 (Jul'22) Dharambir Singh Detail Report
Graph / Photo
169 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2016-17. SH Painting of kerbs and central verge. 2016.12.12 2017.04.10 14.02 Aslam Builders Completed Detail Report
Graph / Photo
170 A/R and M/O to various roads under SRD Division-I, PWD, New Delhi during 2017-18. (SH-Provision of semi permanent office for Sub-Division-II.) 2017.06.25 2017.08.24 13.87 0.00 (Jan'18) 17.31 % (Jan'18) Krishan Kumar Work completed and final bill paid Detail Report
Graph / Photo
171 A/R and M/O to various roads under SRD Division-I, PWD, New Delhi during 2018-19.(SH-Providing and fixing Bollards and other Misc. works at N.S. Marg) 2018.11.30 2019.01.29 13.82 17.01 (Nov'19) 0.00 (Nov'19) M/s. Satyam Construction work in progress Detail Report
Graph / Photo
172 A/R and M/O to various road under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18 SH Misc. Road Repair works under Ballimaran Constituency 2018.02.07 2018.05.07 13.72 Kashi Nath Jha Work Completed Detail Report
Graph / Photo
173 A/R and M/O to various road under PWD SRD Project Division-I, dg. 2018-19 (SH-Provision of yellow coloured maintenance van with required labour and T and P for Chandni Chowk Constituency to attend day to day complaints under Sub Division-I) 2018.08.09 2019.08.08 13.45 6.67 (Nov'19) 0.00 (Nov'19) Sirohi Construction Co. Work completed and final bill paid Detail Report
Graph / Photo
174 A/R & M/O to various road under PWD SRD Project Division-I, dg. 2016-17 (SH: Provision of yellow coloured maintenance van with required labour with T&P to attend day to day maintenance under Sub Division-I). 2017.06.02 2018.06.01 13.40 0.00 (Aug'18) 10.16 % (Aug'18) RANJIT CONSTRUCTION COMPANY Work completed and final bill paid Detail Report
Graph / Photo
175 A/R and M/O to various roads under SRD Project Division-I, New Delhi dg. 2018-19 (SH- Providing services of diesel pumps for removing water logging during rains, under Sub Division-II). 2018.07.01 2018.10.11 13.37 0.00 (Nov'18) 16.30 % (Nov'18) Satyam Construction Company Work Completed and final bill paid Detail Report
Graph / Photo
176 A/R and M/O other PWD Roads under SRD Division-I, PWD, New Delhi during 2018-19. (SH-Painting of Kerb Stones and Other Misc. Work on various roads for Independence Day and Diwali festival under Sub Division-I.) 2018.07.30 2018.11.29 13.24 Arif Work completed and final bill paid Detail Report
Graph / Photo
177 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Repair of footpath and Improvement of Drainage system on Gali No. 10 2018.02.08 2018.05.09 12.78 TKN Developers Work Completed Detail Report
Graph / Photo
178 A/R and M/O various Roads under SRD Project Division-II, PWD, New Delhi during 2016-17. SH Desilting of drains by Super Sucker Machine. 2017.01.09 2017.07.07 12.41 Sai Tubewell Completed Detail Report
Graph / Photo
179 A/R and M/O to various roads under SRD Project Division-I, New Delhi during 2017-18. (SH-Providing and Laying of NP-2 Pipe lines at different locations on various roads for proper drainage during monsoon season under Sub Division-I) 2017.06.16 2017.08.15 12.10 0.00 (Apr'18) 22.62 % (Apr'18) RANJIT CONSTRUCTION COMPANY Work completed and final bill paid Detail Report
Graph / Photo
180 A/R and M/O to various roads under SRD Project Division-I, New Delhi dg. 2017-18 (SH-Providing services of diesel pumps for removing water logging during rains, under Sub Division-I and II). 2017.06.02 2017.09.14 11.93 0.00 (Feb'18) 11.66 % (Feb'18) Satyam Construction Company Work completed and final bill paid. Detail Report
Graph / Photo
181 A/R and M/O to various road under PWD SRD Project Division-I, dg. 2017-18 (SH-Provision of yellow coloured maintenance van with required labour with T and P for Chandni Chowk constituency to attend day to day Complaints under Sub Division-I) 2017.07.20 2018.07.19 11.77 K.P. Singh & Co. Work completed and final bill paid Detail Report
Graph / Photo
182 A/R M/O Old Saint Stephon College building at K.Gate Building, C.P.O Building, Old Court Building, N.C.C offices buildings, N.C.C offices buildings Chabi Ganj, Novelty Fire Station, Fire Station Jama Masjid, Disability Commissioner office, Nayak Se 2018.11.08 2019.11.07 11.61 12.58 (Jan'20) 0.00 (Jan'20) ANSHUL SINGH WORK IN PROGRESS Detail Report
Graph / Photo
183 A/R & M/O various Roads under SRD Project Division-II, PWD, New Delhi during 2016-17. SH: Providing Water Tanker with Hydraulic Jet Facilities for day to day cleaning of Kerb Stone, Crash Barrier, Central Verge, Footpath, Railing, Plants and Planters etc. 2017.01.13 2017.07.21 11.44 Madhu Construction Co. Work Completed Detail Report
Graph / Photo
184 A/R and M/O to various roads under SRD Project Division-I during 2017-18. (SH-Providing and Laying of NP-2 Pipe lines at different locations on various roads for proper drainage during monsoon season under Sub Division-II) 2014.06.04 2017.08.03 11.39 0.00 (Mar'18) 14.12 % (Mar'18) RANJIT CONSTRUCTION COMPANY Work completed final bill paid Detail Report
Graph / Photo
185 Providing of Rain Water Harvesting System at Mayapuri Road and Nangloi-Najafgarh Road under PWD Division West Road-1 2022.07.18 2022.08.16 11.15 Mradul Pratap Singh Detail Report
Graph / Photo
186 A/R and M/O to Various Roads under PWD SRD Project Division-I, during 2017-18. (SH-Disposal of unclaimed malba, building rubbish etc. from the various roads under Sub Division-I.) 2017.05.26 2018.05.25 9.60 0.00 (Apr'18) 10.59 % (Apr'18) TKN Developers Work Completed and final bill paid Detail Report
Graph / Photo
187 A/R and M/O other PWD Roads under SRD Project Division-I, PWD, New Delhi during 2017-18. (SH- Painting of Kerb Stones on various roads before Independence Day under Sub-Division-II.) 2017.08.11 2018.05.10 9.40 0.00 (Apr'18) 5.92 % (Apr'18) Mohd. Asif Work completed and final bill paid Detail Report
Graph / Photo
188 Construction of Drain from YC Electrical Vehicle Shop to Subhash Nagar Drain on 100’ Road Patel Chowk Road under Sub-Div. WR-15, Division West-Road -1. dg. 2022-23 2022.05.27 2022.09.23 9.05 Sanjay Enterprises Detail Report
Graph / Photo
189 A/R & M/O various road under division M-442 during 2014-15 (Disposal of malba from various roads) 2014.05.31 2015.03.30 8.94 B.M. & Sons                                                 Detail Report
Graph / Photo
190 A/R and M/O various PWD roads under SRD Division-I, PWD, New Delhi during 2019-20 (SH- Supply of Material for various roads under Sub Division-I) 2019.08.11 2019.08.25 8.88 5.06 (Sep'19) 0.00 (Sep'19) TKN Developers Detail Report
Graph / Photo
191 A/R and M/O various road under SRD Project Division-I, Sub-Division-I, PWD, New Delhi dg. 2019-20 (SH- Providing and installation of height guage on both side for restriction of heavy vehicles movement at Pul Mithai Bridge and Pul Duffr in Bridge at 2019.07.02 2019.08.01 8.77 10.92 (Mar'21) 0.00 (Mar'21) TKN Developers Detail Report
Graph / Photo
192 A/R and M/O to various Residential Building under SRD Division-I, SRD Sub-Division-III, PWD, Delhi during 2018-19. (SH-Misc., Repair Work in Minister Bungalow No. 217). 2018.07.29 2018.09.11 8.31 0.00 (Jan'19) 10.30 % (Jan'19) Intkahb Alam Work completed and final bill paid Detail Report
Graph / Photo
193 A/R and M/O other Roads under SRD Division-I, PWD, New Delhi during 2018-19.(SH-Painting of Kerb Stones on various roads, under Sub-Division-II.) 2018.07.27 2019.03.26 8.23 0.00 (Apr'19) 9.67 % (Apr'19) Mudassir Hussain Work Completed and final bill paid Detail Report
Graph / Photo
194 A/R and M/O to various roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Painting of Kerb Stone and central Verge. 2018.02.09 2018.08.08 8.20 3.77 (Mar'22) 0.00 (Mar'22) Mudassir Husain A letter has been written for proposal to rescind the work. Detail Report
Graph / Photo
195 A/R and M/O PWD Roads under SRD Division-I, Sub-Division-I, PWD, New Delhi during 2018-19. (SH-Providing water tanker with Hydraulic Jet Facilities for day to day cleaning of kerb stone, crash barrier, footpath, railling, plants and planter etc.) 2018.06.02 2018.12.01 7.20 17.90 (Oct'19) 0.00 (Oct'19) TKN Developers Work in progress Detail Report
Graph / Photo
196 A/R and M/O to IGDTUW at Kashmere Gate, Delhi During 2018-19. (SH-Renovation of Pro Vice Chancellor Room and Room No. 218, 219 and 215 under SRD Division-I, Sub-Division-III, PWD, New Delhi.) 2018.07.19 2018.09.01 6.75 6.33 (Sep'19) 0.00 (Sep'19) Intkahb Alam Work completed final bill yet to be paid Detail Report
Graph / Photo
197 A/R and M/O Old Saint Stephon College building at K.Gate Building C.P.O Building, Old Court Building, N.C.C offices buildings N.C.C offices buildings Chabi Ganj Novelty Fire Station Fire Station Jama Masjid Disability Commissioner office Lok Naya 2018.11.09 2019.11.08 6.74 Kamal Construction Co. work in progress Detail Report
Graph / Photo
198 Road Restoration (balance work) B-Block Road, Mangolpuri cut by Delhi Jal Board 2022.06.12 2022.06.26 6.43 Sanjay Kaura Detail Report
Graph / Photo
199 Providing and operating mobile maintenance vehicle under Sub Division M-2 under section - 1 and section-2. 2019.07.29 2019.09.26 6.35 7.76 (Dec'19) 0.00 (Dec'19) Ashok Kumar Rathi P.G. letter issued Detail Report
Graph / Photo
200 Repair and Refixing of the duct slabs and providing Jersey Barrier. 2017.08.24 2017.10.23 6.35 0.00 (Dec'17) 7.23 % (Dec'17) B P Rai and Sons Work completed and final bill paid Detail Report
Graph / Photo
201 A/R & M/O various Road under Sub-Division M-2113 during 2019-20. (SH: Improvement of Road No. 57 near Swarn Cinema Culvert.). 2020.05.28 2020.06.26 6.27 6.12 (May'21) 0.00 (May'21) Nation Star Enterprises work in progress Detail Report
Graph / Photo
202 Desilting of Sump well of Shakti Nagar, Sawan Park, Roshanara Bagh i/c Repairing of Pump, all around the year 2022.06.12 2023.06.11 5.89 Kuldeep Traders Detail Report
Graph / Photo
203 A/R and M/O other PWD roads under SRD Project Division-I, PWD, New Delhi during 2017-18 (SH- Essential miscellaneous ancillary work for various roads under Sub Division-I). 2017.07.01 2017.07.30 4.98 0.00 (Sep'17) 5.99 % (Sep'17) TKN Developers work completed and final bill paid Detail Report
Graph / Photo
204 Road Restoration of various roads under SRD Project Division-I, PWD, New Delhi during 2017-18. (SH-Repair of the road/ footpath cut by BSES Yamuna Power Limited for laying of Stringing on Chandni Chowk Road under Sub-Division-I) 2017.07.01 2017.08.31 4.96 0.00 (Feb'18) 5.73 % (Feb'18) RANJIT CONSTRUCTION COMPANY Work completed and final bill paid Detail Report
Graph / Photo
205 A/R and M/O other PWD Roads under SRD Division -I, PWD, New Delhi during 2019-20. (SH- Painting of Kerb Stones on various roads before Independence Day under Sub Division-I.) 2019.08.13 2019.08.27 4.45 5.20 (Nov'19) 0.00 (Nov'19) Mohd Arshad Detail Report
Graph / Photo
206 A/R and M/O to various road under PWD SRD Project Division-I, PWD, New Delhi dg. 2017-18 (SH-Supplying, Commissioning, installing and testing of Desktop, UPS and Printer in Circle Office, Division Office and Sub Division-II and III). 2017.07.03 2017.07.17 4.40 0.00 (Jul'17) 5.12 % (Jul'17) Network Infotech Work completed and final bill paid Detail Report
Graph / Photo
207 Providing and fixing Retro Reflective Signage Board on various roads under SRD Project Sub Division I SRD Project Division II PWD New Delhi. 2018.10.12 2018.11.10 4.35 4.15 (Aug'20) 0.00 (Aug'20) Mohan KUMAR Work completed Detail Report
Graph / Photo
208 Providing speed calming measures near Golcha Cinema Dariyaganj at N.S. Marg under SRD Division-I, PWD, New Delhi. 2018.12.07 2019.01.06 4.18 0.00 (Mar'19) 5.21 % (Mar'19) B P Rai and Sons Work completed final bill paid Detail Report
Graph / Photo
209 A/R and M/O various Roads under SRD Project Sub-Division-III/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Supply of materials for day to day maintenance work. 2018.02.07 2018.06.06 4.03 Kashi Nath Jha Work Completed Detail Report
Graph / Photo
210 AR and MO various Roads under SRD Project Division II PWD New Delhi during 2017-18. SH Provision of inspection vehicle for use of Executive Engineer SRD Project Division II PWD. 2018.04.07 2019.04.06 3.90 4.49 (Sep'20) 0.00 (Sep'20) Ram Prasad Singh & Sons Work Completed Detail Report
Graph / Photo
211 A/R and M/O to various roads under SRD Project Division-I, New Delhi dg. 2019-20 (SH-Providing services of diesel pumps for removing water logging during rains, under Sub Division-II) 2019.07.02 2019.10.08 3.86 Tripurari Prasad Singh Detail Report
Graph / Photo
212 A/R and M/O various Roads under SRD Project Sub-Division-III/SRD Project Division-II, PWD, New Delhi during 2016-17. SH Repair of central verge on New Rohtak Road and fixing of slab on drain. 2017.03.20 2017.05.18 3.84 Sarwar Completed Detail Report
Graph / Photo
213 A/R and M/O various Roads under SRD Project Sub-Division-II/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Supply of materials for day to day maintenance work. 2017.07.16 2017.07.30 3.57 TKN Developers Work completed Detail Report
Graph / Photo
214 A/R and M/O to various roads under SRD Project Division-I, New Delhi dg. 2017-18. (SH-Providing services of Sewerman for cleaning bell mouth, kerb channel, drain etc. and removing water logging during rains under Sub Division-II). 2017.06.22 2017.10.19 3.32 0.00 (Nov'17) 4.12 % (Nov'17) RANJIT CONSTRUCTION COMPANY Work completed and final paid Detail Report
Graph / Photo
215 A/R and M/O to various roads under SRD Project Division-I, PWD, New Delhi during 2018-19. (SH- Providing photocopy machine with operator for the office of SE (Project) and EE, SRD-I). 2019.03.18 2020.03.17 3.21 4.01 (Dec'20) 0.00 (Dec'20) TKN Developers work in progress Detail Report
Graph / Photo
216 A/R &M/O Various Roads under Shahdara Roads Civil Divn PWD during 2020-21. (SH Repair and maintenance of EPABX, KTS, Push button Phone, Plan & Inverter in sub division, Division & Circle office (M-21).) 2020.08.06 2021.08.05 3.07 3.82 (Mar'22) 0.00 (Mar'22) Sagar Systems Work in Progress Detail Report
Graph / Photo
217 AR and MO Various Road under Sub Division M 2111 during 2018 19 SH Providing Height Restricting Barrier for Seelampur Flyover SECTION I 2018.06.05 2018.07.04 1.92 1.08 (Jul'22) 0.00 (Jul'22) DASHRATH KUMAR WORK FORECLOSED Detail Report
Graph / Photo
218 Annual Maintenance of office equipments and its allied items in Office of Superintending Engineer Project, Office of Executive Engineer, SRD Project Division I and Office of Assistant Engineer I, II, III and IV PWD, New Delhi Dg. 2019 20 2019.09.28 2020.02.27 1.01 0.67 (Mar'22) 0.00 (Mar'22) A.N. TECHNOLOGIES Detail Report
Graph / Photo
219 Supply, Installation, Testing and Commissioning and Comprehensive maintenance and operation of 6 Nos. 13 Passenger Capacity Lifts (Machine Room less) 2012.01.08 -- Detail Report
Graph / Photo
220 AR and MO various roads under SWR-II PWD NCTD Delhi dg. 2016-17 SH Desilting of storm water drains at Janakpuri Area Lal Sai Road Vidya Marg Ram Mandir Marg Dabri Road etc. under Sub Divn. I New Delhi. 2017.01.01 2017.06.30 Work Completed Detail Report
Graph / Photo
221 AR and MO various roads under PWD Sub Divn I SWR II during 2016-17 SH Desilting of Drains under Section-I Pankha Road Area New Delhi 2017.06.09 2017.12.05 Work foreclosed on 18/10/2017 Detail Report
Graph / Photo
222 Brick Masonary drain and footpath at Hans Raj Gupta Marg 2014.05.29 2014.10.28 0.00 (Mar'17) 85.00 % (Mar'17) Work is to be foreclosed after connecting with R Block drain. Detail Report
Graph / Photo
223 Construction of back to back u turn on road no. 13 A G.D. Birla Marg, Sarita Vihar, New Delhi 2016.02.20 2016.04.19 0.00 (Feb'17) 50.00 % (Feb'17) Plan showing modified location of U turn as per the demand of local RWA submitted to UTTIPEC for approval Detail Report
Graph / Photo
224 Laying of 1000 mm dia RCC pipe along road no. 13 for disconnection of storm water drain from sewer line to open drain on both side at Tughlakabad Extn, Kalkaji New Delhi 2016.09.05 2016.10.04 30.73 (Mar'17) 35.00 % (Mar'17) Work is held up due to non reciept of permission from Delhi Traffic Police Detail Report
Graph / Photo
225 Improvement of road surface of Hansraj Sethi Marg, Baba Fateh Singh Marg, Maharaja Agarsen Marg and Kashi Ram Takkar Marg 2016.07.16 2016.09.15 191.64 (Mar'17) 75.00 % (Mar'17) Bituminous work completed road marking is yet to be done Detail Report
Graph / Photo
226 Improvement of road surface of Hansraj Gupta Marg 2016.07.16 2016.09.15 111.72 (Mar'17) 85.00 % (Mar'17) bituminous work completed road marking is yet to be done Detail Report
Graph / Photo
227 Bituminous Work 2016.07.26 2016.09.25 0.00 (Mar'17) 5.00 % (Mar'17) work is in progress Detail Report
Graph / Photo
228 Improvement of riding surface of Maharaja Agarsen Marg, Madanpur Khadar Road & Jaiptur Road from Mathura Road to Agra Canal under Division SER-2 during 2016-17 2016.07.25 2016.09.24 69.07 (Mar'17) 15.00 % (Mar'17) paver block in berm on agarsen marg has been fixed resurfacing on Madanpur Khadar Road has also been completed Detail Report
Graph / Photo
229 Improvement of service road of Road No. 13 from Crown Plaza to Sarita Vihar Underpass at New Delhi 2016.08.08 2016.10.07 56.22 (Mar'17) 25.00 % (Mar'17) One side of service road completed in all respect and work is in progress on other side of road Detail Report
Graph / Photo
230 Improvement of Road surface of Saheed Surya Sen Marg and KPS Marg at Alaknanda Area 2016.07.08 2016.09.07 57.40 (Mar'17) 95.00 % (Mar'17) Bituminous work completed. Thermoplastic painting work is to be taken up Detail Report
Graph / Photo
231 Repair of damaged drain & Covering with precast RCC slab on School Road, Gurudwara Road & Jaitpur Road under PWD Division SER-2 during 2016-17 New Delhi. 2016.10.25 2016.12.24 0.00 (Feb'17) 65.00 % (Feb'17) Work is in progress Detail Report
Graph / Photo
232 Improvement of berm of Gurudwara Road from Don Bosco School to Savitri Cinema Road during 2016-17 2016.11.15 2017.02.14 0.00 (Mar'17) 5.00 % (Mar'17) Work is in progress Detail Report
Graph / Photo
233 A/R and M/O various Roads under SRD Project Sub-Division-I/SRD Project Division-II, PWD, New Delhi during 2017-18. SH Supply of materials for day to day maintenance work 2018.04.23 2018.07.21 WORK COMPLETED Detail Report
Graph / Photo
234 A/R and M/O various Roads under SRD Project Division-II, PWD, New Delhi during 2017-18. SH Provision of inspection vehicle for use of Executive Engineer, SRD Project Division 2018.04.07 2019.04.06 Completed (Final Bill yet to be submitted by the agency) Detail Report
Graph / Photo
235 Strengthening of road surface of Outer Ring Road from Modi Mill to Chirag Delhi (Masjid Moth). 2018.05.27 2018.07.26 436.54 (Apr'19) 73.00 % (Apr'19) - Detail Report
Graph / Photo
236 A/Rand M/O various Roads under SRD Project Sub Division III SRD Project Division II PWD, New Delhi,during 2017-18.SH Supply of materials for day to day maintenance work 2018.03.24 2018.06.21 Work Completed Detail Report
Graph / Photo
237 A/R and M/O various roads under SRD Project Sub. Division-III/SRD Project Division-II, PWD, New Delhi during 2018-19 .SH-Desilting through super sucker and manually of various roads drains under sub division- III. 2018.06.19 2018.12.15 WORK COMPLETED Detail Report
Graph / Photo
238 Micro Surfacing of various road under SRD Project Sub division III SRD Project Division II PWD New Delhi during 2017-18. SH Micro Surfacing and improvement of footpath at Khajoor Road. 2018.08.17 2018.12.14 25.48 (Nov'20) 0.00 (Nov'20) WORK COMPLETED Detail Report
Graph / Photo
239 AR and MO various roads under SRD Project Sub Division III SRD Project Division II PWD New Delhi during 2018-19 SH Desilting through super sucker and manually of various roads drains under sub division III 2018.06.19 2018.12.15 WORK COMPLETED Detail Report
Graph / Photo
240 Providing and laying RMC in berm portion and repairing of footpath of Hansraj Sethi Marg and Kanshi Ram Takkar Marg 2018.05.03 2018.06.02 90% Detail Report
Graph / Photo
241 Re development of planter area for the prevention from the encroachment pollution unauthorised parking ease of movement of public and traffic jam etc at Guru Ravidass Marg under Division SER 2 2018.05.17 2018.08.16 61.76 (Apr'19) 96.00 % (Apr'19) - Detail Report
Graph / Photo
242 Making of missing drain for disposal of storm water near Paras ground side at Nehru Place on Outer Ring Road 2018.05.17 2018.06.16 The work has been completed ... Bill yet to be submit. Detail Report
Graph / Photo
243 AR and MO various roads under SRD Project Sub Division I SRD Project Division II PWD New Delhi during 2018-19 SH Desilting through super sucker and manually of various roads drains under sub division I 2018.06.20 2018.12.16 29.44 (Apr'19) 100.00 % (Apr'19) WORK COMPLETED Detail Report
Graph / Photo
244 AR and MO various roads under SRD Project Sub. Division III SRD Project Division-II PWD New Delhi during 2018-19 .SH Desilting through super sucker and manually of various roads drains under sub division III 2018.06.19 2018.12.15 WORK COMPLETED. Detail Report
Graph / Photo
245 AR and MO Various Road under Sub Division M 2113 During 2018 19 SH Repairing of Drain at Babarpur Road SECTION II 2018.08.07 2018.10.05 Duplicate Work Detail Report
Graph / Photo
246 AR and MO various roads under SRD Project Sub Division II SRD Project Division II PWD New Delhi during 2018-19 SH Desilting through super sucker and manually of various roads drains under sub division II. 2018.06.19 2018.12.15 34.12 (Jan'19) 100.00 % (Jan'19) WORK COMPLETED Detail Report
Graph / Photo
247 Shifting of drain from K Pocket Gate Sarita Vihar to Maharaja Agarsen Road for widening of road at Road No 13 A 2018.06.02 2018.08.01 7.02 (Mar'19) 100.00 % (Mar'19) 100% Detail Report
Graph / Photo
248 Micro Surfacing of various road under SRD Project Sub division-III SRD Project Division II, PWD , New Delhi during 2017-18. SH Micro Surfacing and improvement of footpath at Khajoor Road. 2018.08.17 2018.12.14 Work completed. Detail Report
Graph / Photo
249 Hiring of inspection vehicle for EE SER 2 2018.06.17 2019.06.16 4.53 (May'19) 77.00 % (May'19) 95% Detail Report
Graph / Photo
250 Raising of manhole cover and making connection to the old drain with manhole chambers 2018.07.17 2018.08.16 Work is in progress. Detail Report
Graph / Photo
251 Disposal and Removal of dumped malba 2019.03.30 2019.09.29 4.73 (May'19) 0.00 (May'19) The 25% work has been completed and left work is in progress.. Detail Report
Graph / Photo
252 Watch and ward of Subways under Sub Division SER-23 and SER-25 2018.06.24 2019.06.23 90% Detail Report
Graph / Photo
253 Providing and running diesel pump set 2018.07.01 2018.09.30 2.27 (Jun'19) 0.00 (Jun'19) 100% Detail Report
Graph / Photo
254 Micro surfacing of various Road under SRD Project Sub Division I SRD Project Division II PWD New Delhi SH Micro surfacing and Improvement of footpath at Chitra Gupta Road 2018.10.25 2019.02.21 81.57 (Nov'20) 0.00 (Nov'20) WORK COMPLETED Detail Report
Graph / Photo
255 Providing services for special inspection, analysis of existing structure, conducting tests and preparation of remedial measures report including Bill of Quantities (BOQ) for Repair and Rehabilitation of Seelampur Flyover Delhi 2019.02.18 2019.05.18

Work in progress

Detail Report
Graph / Photo
256 Providing and fixing M.S. Grill on footpath near FOB at Sarita Vihar Mathura Road 2018.09.13 2018.10.28 5% Detail Report
Graph / Photo
257 Providing services for special inspection, analysis of existing structure conducting tests and preparation of remedial measures report including BOQ for Repair and Rehabilitation of Seelampur Flyover Delhi 2019.02.18 2019.05.18

Work in progress

Detail Report
Graph / Photo
258 Providing JCB and Dumper with labours for removing temporary encroachment and collecting dumped malba 2018.11.02 2019.05.01 Work is completed ... Bill not submit yet.. Detail Report
Graph / Photo
259 Construction of missing drain and widening of road due to heavy traffic jam etc at Road No. 13 A 2018.11.24 2019.02.23 37.17 (May'19) 0.00 (May'19) 50% Detail Report
Graph / Photo
260 A R and M O various road under Sub Division M 2113 during 2018 19 SH Covering of drain of Babarpur Road after necessary misc repair work SECTION II Balance Work RECALL 2018.10.28 2019.02.24 Work in progress Detail Report
Graph / Photo
261 Supply of sand stone aggregate and Bitumen emulsion for all Sub Divisions 2018.12.17 2018.12.23 - Detail Report
Graph / Photo
262 Repair and beautification of kabootar chowk T Point of SA Road near Kalkaji Mandir and Hansraj Sethi Marg near Nehru Place 2018.12.31 2019.01.30 - Detail Report
Graph / Photo
263 Construction of toe wall near Tehkhand Depot 2018.12.31 2019.02.28 16.03 (Jun'19) 0.00 (Jun'19) - Detail Report
Graph / Photo
264 Raising and repair of footpath on Road No. 13 from Guru Ravi Dass Marg T Point to Crowne Plaza 2018.12.31 2019.01.30 - Detail Report
Graph / Photo
265 Repair of damaged footpath from SA Road T Point to RUB Badarpur MB Road 2018.12.31 2019.01.30 - Detail Report
Graph / Photo
266 Improvement of kerb wall on Okhla Estate Marg (Road No 13) from Guru Ravi Dass Marg T Point to Aggarwal sweets 2019.02.25 2019.03.24 9.78 (May'19) 0.00 (May'19) The 60% work has been completed and the rest work is in progress. Detail Report
Graph / Photo
267 Provision of table top/speed breaker on PWD roads in GK-2. 2019.02.18 2019.03.01 - Detail Report
Graph / Photo
268 Beautification of surrounding area near Delhi Institute of Tool Engineering at SA Road 2019.02.24 2019.03.25 10.84 (May'19) 0.00 (May'19) - Detail Report
Graph / Photo
269 Providing and laying RCC kerb stone at roundabout at Hansraj Sethi marg 2019.02.18 2019.03.19 - Detail Report
Graph / Photo
270 Road Restoration of Bipin Chander Pal Marg 2019.02.17 2019.03.18 The 60% work has been done and the left work is in progress... Detail Report
Graph / Photo
271 Improvement of kerb wall on Okhla Estate Marg (Road No 13) from Guru Ravi Dass Marg T Point to Aggarwal sweets. 2019.02.25 2019.03.26 The 60% work has been done.... Detail Report
Graph / Photo
272 Repair and Improvement of footpath from primary school lal Kuan to Suraj Kund crossing at MB Road. 2019.02.09 2019.04.08 - Detail Report
Graph / Photo
273 Repair of central verge and P/F of missing grill and other misc works at MB Road. 2019.02.09 2019.03.10 75% Detail Report
Graph / Photo
274 A R and M O to various roads under subdivision III SRD project division II Delhi dg 2018 19 SH Laying of NP 2 pipe repair of footpath at Hardhyan Singh road between road 3 to road no 4 pyare lal road between road no 3 to DB Gupta road and Guru Ravida 2019.08.16 2019.11.13 Work in progress Detail Report
Graph / Photo
275 Restoration of various roads under SRD Project Sub Division I of SRD Project Division II PWD dg 2019 20 SH Repair of roads and footpath cut by various utility services agencies 2019.08.06 2019.10.04 Work in progress Detail Report
Graph / Photo
276 Providing and fixing 6 feet high M.S. Railing on central verge of MB Road 2019.03.23 2019.04.22 - Detail Report
Graph / Photo
277 A R and M O to various roads under subdivision III SRD project division II Delhi dg 2018 19 SH Laying of NP 2 pipe repair of footpath at Hardhyan Singh road between road 3 to road no 4 pyare lal road between road no 3 to DB Gupta road and Guru Ravida 2019.08.16 2019.11.13 work in progress Detail Report
Graph / Photo
278 Providing and fixing M. S. Grill at central verge from Chhawla Village to BDO office, at Najafgarh Bijwasan Road (ID 1173) under PWD division SWR-II, New Delhi. 2020.09.14 2020.10.13 WORK not started Detail Report
Graph / Photo
279 Restoration of various roads under SRD Project Sub. Division II SRD Project Division II PWD New Delhi. SH Restoration of various road cuts by IGL and Vodafone at New Rohtak Road under Sub Division II tion of various road 2019.07.22 2019.10.19 Work in progress Detail Report
Graph / Photo
280 feasibility studies for the corridor network UG Tunnel and improvement of existing Dwarka Road from NH 8 to Dwarka 2019.12.28 2020.06.24 Work In progress Detail Report
Graph / Photo
281 Raising of manhole height of storm water drain on Mathura road 2019.04.26 2019.06.10 0% Detail Report
Graph / Photo
282 Repair of footpath Outer Ring Road from Modi Mill to Kabootar Chowk and Providing and fixing carbonate sheet of FOB 2019.04.18 2019.05.17 The work is in progress... Detail Report
Graph / Photo
283 Supply and stacking of material 2019.04.09 2019.04.18 40% Detail Report
Graph / Photo
284 Repair of footpath Jaitpur Road. 2019.02.21 2019.04.20 95% Detail Report
Graph / Photo
285 A/R and M/O various road under SER-2/25 during 2018-19 (SH- Removal of grass and malba from central verge and side berms) 2019.03.30 2019.04.28 The 70% work has been completed.. Detail Report
Graph / Photo
286 Raising of height of central verge SA Road from crowne plaza to MB Road T Point 2019.03.30 2019.04.28 - Detail Report
Graph / Photo
287 Disposal of dumped malba 2019.03.30 2019.09.29 The 25% work has been completed and rest work is in progress... Detail Report
Graph / Photo
288 Repair of berm portion of Nehru Enclave Service road on Outer Ring Road 2019.03.30 2019.04.29 The 80% work has been completed and the rest work is in progress. Detail Report
Graph / Photo
289 Repair of damage footpath Hansraj Sethi Marg from EPDP Road to Nehru Place Flyover 2019.03.30 2019.04.28 - Detail Report
Graph / Photo
290 Development of open space at SA Road from DJB UGR to MCD SLF 2019.04.16 2019.06.14 60% Detail Report
Graph / Photo
291 Providing watch and ward for Sub Division office 2019.03.15 2019.09.14 - Detail Report
Graph / Photo
292 Mechanical desilting of road side storm water drain and sewer mixed drains by super sucker machine on MB Road and Suraj Kund Road and 5 Nos cross culvert 2019.03.10 2019.10.05 - Detail Report
Graph / Photo
293 Mechanical desilting of road side storm water drain and sewer mixed drains by Super Sucker Machine on Guru Ravi Dass Marg, KPS Marg and DDA Market Road 2019.03.10 2019.10.05 - Detail Report
Graph / Photo
294 Mechanical desilting of road side storm water drain and sewer mixed drains by super sucker machine on Outer Ring Road, Hansraj Gupta Marg, R Block Road, Guru Nanak Market to Lala Lajpat Rai.. 2019.03.09 2019.10.04 - Detail Report
Graph / Photo
295 Restoration of SA Road, Hansraj Sethi Marg, Baba Fateh Singh Marg. 2019.03.01 2019.03.15 - Detail Report
Graph / Photo
296 Repair of service road at Pul Pehladpur. 2019.03.01 2019.05.31 - Detail Report
Graph / Photo
297 Construction of boundary wall near Giri Nagar, Maharaja Agarsen Marg. 2019.03.01 2019.04.30 - Detail Report
Graph / Photo
298 Providing and placing jersey barrier on Madanpur Khadar Road. 2019.03.02 2019.03.16 11.11 (Jun'19) 0.00 (Jun'19) - Detail Report
Graph / Photo
299 Providing and placing jersey barrier on Meethapur chowk in Jaitpur area. 2019.03.04 2019.03.18 0% Detail Report
Graph / Photo
300 Remodelling and construction of missing drain at R Block Road GK-I 2019.03.10 2019.05.08 - Detail Report
Graph / Photo
301 Repair and renovation of Sub Division office 2019.03.15 2019.04.13 The work is in progress.. Detail Report
Graph / Photo
302 Repair of footpath, Baba Fateh Singh Marg from SA Road to Guru Ravi Dass Marg 2019.03.18 2019.04.16 - Detail Report
Graph / Photo
303 Providing and laying RMC at berm portion of KPS Marg 2019.03.15 2019.04.13 - Detail Report
Graph / Photo
304 Providing and fixing of M.S. Railing at the footpath of Guru Ravi Dass Marg 2019.03.23 2019.04.21 75% Detail Report
Graph / Photo
305 Repair of damaged footpath and drain Guru Ravi Dass Marg from MB Road T Point to Road No. 13 Red Light 2019.04.14 2019.06.13 90% Detail Report
Graph / Photo
306 Repair of damage footpath Maharaja Agarsen Marg and Kanshi Ram Takkar Marg 2019.03.25 2019.04.24 - Detail Report
Graph / Photo
307 Repair of damage footpath KPS Marg 2019.03.25 2019.04.23 - Detail Report
Graph / Photo
308 Improvement of SA Road T Point Junction 2019.03.30 2019.05.28 - Detail Report
Graph / Photo
309 Providing and Fixing Speed Calming measures at Guru Govind Singh Marg, Maharishi Dayanand Marg, Outer Ring Road, Anuvrat Marg, Basant Kaur 2020.12.03 2021.03.02 49.92 (Jan'22) 0.00 (Jan'22) Work in Progress. Detail Report
Graph / Photo
310 Re-surfacing of Service Roads of Outer Ring Road from Chirag Delhi Flyover to Panchsheel Flyover cut by various agencies under Sub Division-4 of Division South Road-2, PWD during 2021-22 2021.10.02 2022.01.01 72.95 (Jul'22) 0.00 (Jul'22) Work in Progress. Detail Report
Graph / Photo
311 Construction of Two No Foot Over Bridge across (i)Sri Aurobindo Marg (ID-96) at Adhchini Village (ii) Hauz Khas Enclave (Near Padmini Enclave) with staircase and lift including Electrical Installation under Sub Division-II of Division South Road-II 2020.03.21 2020.09.20 207.36 (Jun'22) 0.00 (Jun'22) Work in Progress. Detail Report
Graph / Photo
312 Rehabilitation and strengthening of Janak Setu Flyover in New Delhi (Balance Work) 2020.03.29 2020.09.29 23.39 (Sep'21) 0.00 (Sep'21)

Work in progress

Detail Report
Graph / Photo
313 Repair and Rehabilitation of Vehicular Under Pass (VUP) and its approaches and Approaches of three RoBs at PulMithai on SPM Marg, Delhi 2020.01.16 2020.10.15 40.81 (Apr'21) 0.00 (Apr'21)

Work in progress

Detail Report
Graph / Photo
314 Structural audit of flyovers of New Nizamuddin Flyover,Nehru Place Flyover,Sarita Vihar flyover,Andrews Ganj Flyover 2020.03.05 2021.05.28 40.80 (Sep'21) 0.00 (Sep'21)

Work in progress

Detail Report
Graph / Photo
315 Structural audit of flyovers of Tilak Nagar flyover near metro station,Punjabi Bagh Club flyover,Raja Garden Flyover,Tilak Nagar flyover near District Centre,Peera Garhi flyover 2020.03.05 2021.05.28

Work in progress

Detail Report
Graph / Photo
316 Repair of footpath at various locations on Nelson mandela road under Sub division V 2022.04.04 2022.06.03 Work in progress Detail Report
Graph / Photo