S. No.क्र. सं. | Project Name | A/A & E/S |
Date of Start
Completion Expected |
Expenditure
Progress |
Remarks | View |
---|---|---|---|---|---|---|
1 | C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) |
2892.65 Cr. 14/08/2018 F-18/Estate/Constn. 12748 Eq. Cls/Priority-II/PWD/2975-80 |
29/12/2018 26/07/2019 30/11/2022 |
38.76 Cr. (Jul'22) 0.00 (Jul'22) |
Work in progress |
Detail Report
Graph / Photo |
2 | RPVV Lajpat Nagar, School ID : 1925334 |
2892.65 Cr. 14/08/2018 (F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.) |
08/12/2018 04/08/2019 31/10/2022 |
26.59 Cr. (Oct'22) 0.00 (Oct'22) |
Work is in progress |
Detail Report
Graph / Photo |
3 | Co-Ed. SSS Lajpat Nagar, School ID: 1925335 |
2892.65 Cr. 14/08/2018 (F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.) |
08/12/2018 04/08/2019 31/10/2022 |
0.00 Cr. (Sep'21) 60.00 % (Sep'21) |
Work is in progress |
Detail Report
Graph / Photo |
4 | GBSSS Jungpura, School ID : 1924004 |
2892.65 Cr. 14/08/2018 (F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.) |
08/12/2018 04/08/2019 31/10/2022 |
27.55 Cr. (Dec'21) 0.00 (Dec'21) |
Work is in progress |
Detail Report
Graph / Photo |
5 | GGSSS Dera Village School ID: 1923023 |
2892.65 Cr. 14/08/2018 (F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.) |
08/12/2018 04/08/2019 30/11/2022 |
17.39 Cr. (Oct'22) 0.00 (Oct'22) |
In progress |
Detail Report
Graph / Photo |
6 | GBSSS Dera Village School ID: 1923360 |
2892.65 Cr. 14/08/2018 (F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.) |
08/12/2018 04/08/2019 30/11/2022 |
0.00 Cr. (Feb'21) 63.00 % (Feb'21) |
In progress |
Detail Report
Graph / Photo |
7 | C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) |
2892.65 Cr. 14/08/2018 F-18/Estate/Constn. 12748 Eq. Cls/Priority-II/PWD/2975-80 |
20/01/2019 15/11/2019 31/10/2022 |
38.84 Cr. (Oct'22) 0.00 (Oct'22) |
Work in progress |
Detail Report
Graph / Photo |
8 | C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) |
2892.65 Cr. 14/08/2018 . F-18/Estate/Constn. 12748 Eq. Cls/Priority-II/PWD/2975-80 |
14/01/2019 09/11/2019 31/10/2022 |
47.00 Cr. (Oct'22) 0.00 (Oct'22) |
Work in progress |
Detail Report
Graph / Photo |
9 | Construction of Hospital at Madipur, New Delhi |
320.07 Cr. 06/12/2019 F.8(A)/(10)/DGHS/HC/2019/CD#112557061/Js3hfw-3999-4016 |
11/11/2020 10/11/2022 10/11/2022 |
43.72 Cr. (Oct'22) 0.00 (Oct'22) |
RCC of terrace floor slab is completed. Masonry work at 8th & 9th floor is in progress. Finishing work such as tile work, granite work, POP, putty etc. in progress in 1st to 6th floor. |
Detail Report
Graph / Photo |
10 | Providing service of Photocopier Machine on rental basis in the Office of Executive Engineer, Health Project Division Central, PWD, Lok Nayak Hospital, New Delhi |
320.07 Cr. 06/12/2019 F.8(A)/(10)/DGHS/HC/2019/CD#112557061/Js3hfw-3999-4016 |
-- -- -- |
|
work completed.. |
Detail Report
Graph / Photo |
11 | Providing service of Photocopier Machine on rental basis in the Office of Executive Engineer, Health Project Division (Central), PWD, Lok Nayak Hospital, New Delhi |
320.07 Cr. 06/12/2019 F.8(A)/(10)/DGHS/HC/2019/CD#112557061/Js3hfw-3999-4016 |
-- -- -- |
|
work in progress. |
Detail Report
Graph / Photo |
12 | C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road, Delhi (SH: C/o Academic Blocks AB-3 & AB-4, Boys Hostel H-5 & Girls Hostels HG-5 & HG-6 and all external and internal services including external development and landscaping, and allied civil and E&M works). |
291.88 Cr. 11/09/2018 75(8)/DTTE/Plg EFC/2013-14/000323618/527-33 dated 11.09.2018 |
23/09/2019 23/12/2020 16/10/2022 |
30.27 Cr. (Oct'22) 0.00 (Oct'22) |
Boys Hostel and Girls Hostel has been completed. Academic Building is in final stage of completion. Work Provisionally completed on 27.09.2022 and handing over building is in progress. |
Detail Report
Graph / Photo |
13 | Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II.(Package-F) |
289.27 Cr. 14/08/2018 ( Consolidated sanction amount 2892.65 ) F-18/Estate/Cont. 12748 Egu.Cls/Priority-II/PWD/2975-80 |
27/01/2019 23/10/2019 31/10/2022 |
37.75 Cr. (Oct'22) 0.00 (Oct'22) |
Work in progress. |
Detail Report
Graph / Photo |
14 | Construction of Hospital at Hastsal, New Delhi |
211.12 Cr. |
17/06/2021 16/06/2023 16/06/2023 |
|
15% |
Detail Report
Graph / Photo |
15 | Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). |
209.59 Cr. 27/11/2015 No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre) |
25/01/2019 24/05/2019 30/09/2020 |
2.16 Cr. (Oct'21) 0.00 (Oct'21) |
work in progress |
Detail Report
Graph / Photo |
16 | Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi |
209.59 Cr. 27/11/2015 No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre) |
27/12/2018 26/04/2019 -- |
3.36 Cr. (Aug'21) 0.00 (Aug'21) |
work completed |
Detail Report
Graph / Photo |
17 | Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
194.91 Cr. 25/06/2018 2(11)/PWD-Upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45 |
04/03/2020 03/09/2021 03/09/2021 |
21.82 Cr. (Oct'22) 0.00 (Oct'22) |
work in progress |
Detail Report
Graph / Photo |
18 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi |
172.03 Cr. 22/06/2018 F.4/261/PWD/Health/2016/GGSH CD#112412717/2492-2509 dated 22.06.2018 |
18/10/2019 10/04/2021 12/12/2022 |
27.30 Cr. (Oct'22) 0.00 (Oct'22) |
Work is under progress. |
Detail Report
Graph / Photo |
19 | Construction Of New 460 Bed Mother & Child Hospital Building At Khichripur , Delhi |
143.73 Cr. 12/06/2019 A/A & E/S is issued by Sh. R.C. Kesarwani, Joint Secretary (H&FW) vide No. F.61/02/2006-07/Estt./LBSH/Pt. File CD#000384462/Jsshfw -1387-1405 dated 12 |
08/01/2020 01/04/2021 30/11/2022 |
6.76 Cr. (Oct'22) 0.00 (Oct'22) |
Work was delayed mainly due to COVID-19 pandemic in 2020 & 21. MLCP structure above ground floor and connection of new building to existing building is to be decided. 7th & above floors casting in progress by parts. |
Detail Report
Graph / Photo |
20 | C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. |
117.78 Cr. 22/06/2018 5/171/SGMH/TCSUB/CT/2016 CD# 112388502/2510-2527 |
04/09/2019 03/03/2021 31/12/2022 |
10.74 Cr. (Oct'22) 0.00 (Oct'22) |
work in progress. |
Detail Report
Graph / Photo |
21 | Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) |
101.63 Cr. |
18/07/2021 17/07/2022 17/07/2023 |
5.14 Cr. (Oct'22) 0.00 (Oct'22) |
Work is in progress. |
Detail Report
Graph / Photo |
22 | Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A6 Paschim Vihar, New Delhi (Package - 7). |
101.63 Cr. |
18/07/2021 17/07/2022 17/07/2023 |
0.00 Cr. (Sep'22) 0.00 (Sep'22) |
Work is in progress. |
Detail Report
Graph / Photo |
23 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. |
86.31 Cr. 23/03/2018 F. RTRMH-I/9/PWD(13)/2015-16/CD#000384488/1223-39 |
06/08/2019 29/10/2020 31/12/2022 |
6.02 Cr. (Oct'22) 0.00 (Oct'22) |
Work is under progress. |
Detail Report
Graph / Photo |
24 | Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2) |
83.39 Cr. 26/03/2018 F/10/Estate/Renovation of staff rooms/951 schools/DoE/945-50 |
-- -- -- |
|
Detail Report
Graph / Photo |
|
25 | Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). |
83.38 Cr. 30/07/2018 Chief Engineer |
23/03/2019 22/09/2019 22/09/2019 |
0.94 Cr. (Sep'22) 0.00 (Sep'22) |
Work in progress |
Detail Report
Graph / Photo |
26 | Upgradation of 3 Nos staff rooms of GNCTD Schools under Jurisdiction of DHC Division PWD dg 2018 19 |
83.38 Cr. 26/03/2018 The A/A & E/S of Rs. 83,38,36,800/- has been received from Deptt. of Education vide letter no. F.16/Estate/Renovation staffrooms/951Schools/DoE/945-50 |
25/12/2018 22/02/2019 30/06/2019 |
0.18 Cr. (Nov'20) 0.00 (Nov'20) |
Work in progress |
Detail Report
Graph / Photo |
27 | Upgradation of One Staff room in each of 951 Schools under Delhi Govt Sh Upgradation of staff rooms at various schools 25 Nos including Civil and Electrical works under CBMD M 323 Delhi Composite work |
83.38 Cr. 26/03/2018 pl. Director of Education (Finance) vide letter No. F 16/Estate/Renovatin of Staff rooms/951 school/ DOE/945-50 dt. 26-03-2018 for Rs. 833836800/- Tot |
-- -- -- |
0.28 Cr. (Aug'20) 0.00 (Aug'20) |
Detail Report
Graph / Photo |
|
28 | Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). |
83.38 Cr. 26/03/2018 F.16/estate/renovation of staff rooms/951 Schools/DOE/945-50 dated 26.03.2018 for Rs. 83,38,36,800/- |
11/02/2019 10/06/2019 10/06/2019 |
5.40 Cr. (Jul'22) 0.00 (Jul'22) |
WORK IN PROGRESS |
Detail Report
Graph / Photo |
29 | Upgradation/Renovation of one staff room in each of 73 schools (Morning and Evening Shift) located at (NE) District of Delhi under the jurisdiction of PWD Building Maintenance Division M-222 |
68.37 Cr. 26/03/2018 No. F.16/Estate/ Renovations of staff rooms/ 951 school/Dof/945-50 dated 26-3-2018 |
25/01/2019 24/04/2019 30/09/2019 |
1.93 Cr. (Jan'22) 0.00 (Jan'22) |
work completed |
Detail Report
Graph / Photo |
30 | Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 |
68.00 Cr. 31/07/2013 7.73 Crores corresponding to this work |
30/09/2014 26/05/2015 31/01/2016 |
0.61 Cr. (May'19) 0.00 (May'19) |
Work completed on 31/12/2017 final payment yet to be made |
Detail Report
Graph / Photo |
31 | Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site, RWHS, STP, Furniture etc at Sector 18, Rohini. (SH: Civil and Electrical Composite Work). |
45.37 Cr. 02/09/2019 F.16/Estate/Const. Pucca School Building/Sector-18/Rohini/4824-4830 |
23/05/2020 23/05/2021 31/12/2022 |
12.28 Cr. (Oct'22) 0.00 (Oct'22) |
Work in progress |
Detail Report
Graph / Photo |
32 | C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Daryapur kalan, Delhi. |
43.70 Cr. 02/09/2019 F.16/Estate/Const.Pucca School Building/Dariyapur Kalan/4775-81 |
30/05/2020 29/05/2021 31/10/2022 |
0.00 Cr. (Nov'21) 30.00 % (Nov'21) |
Structure work completed. Outsde clading work 90% completed. Outer development work like UG Tank and septic tank in progress.Coba work on terrace is in progress. Truss work of MP Hall completed and inside finishing in progress. Doors and window work in classroom in progress. |
Detail Report
Graph / Photo |
33 | Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Dariyapur Kalan, Delhi |
43.70 Cr. 02/09/2019 F.16/Estate/Const.Pucca School Building/Dariyapur Kalan/4775-81 |
30/05/2020 29/05/2021 31/10/2022 |
24.52 Cr. (Oct'22) 0.00 (Oct'22) |
Structure work completed. Outsde clading work 90% completed. Outer development work like UG Tank and septic tank in progress.Coba work on terrace is in progress. Truss work of MP Hall completed and inside finishing in progress. Doors and window work in classroom in progress |
Detail Report
Graph / Photo |
34 | C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Libaspur, Delhi. |
43.23 Cr. 02/09/2019 F.16/Estate/Const.Pucca School Building/Libaspur/4789-4795 |
30/05/2020 29/05/2021 31/10/2022 |
0.00 Cr. (Nov'21) 34.00 % (Nov'21) |
Structure work completed. Partition work with bricks are completed. Tile, plaster and granite work is in progress. Truss work of MP Hall completed. Clading work on exterior wall is in progress. Plumbing work is in progress. Coba work on terrace is in progress. Construction of UG tank is in progress. Fixing of doors, windows and grill are in progress. |
Detail Report
Graph / Photo |
35 | Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Libaspur, Delhi |
43.23 Cr. 02/09/2019 F.16/Estate/Const.Pucca School Building/Libaspur/4789-4795 |
30/05/2020 29/05/2021 31/10/2022 |
33.37 Cr. (Oct'22) 0.00 (Oct'22) |
Structure work completed. Partition work with bricks are completed. Tile, plaster and granite work is in progress. Truss work of MP Hall completed. Clading work on exterior wall is in progress. Plumbing work is in progress. Coba work on terrace is in progress. Construction of UG tank is in progress. Fixing of doors, windows and grill are in progress. |
Detail Report
Graph / Photo |
36 | Expansion and Remodelling of Aruna Asaf Ali Govt. Hospital at Rajpur Road, New Delhi. |
37.31 Cr. |
10/08/2019 03/08/2020 03/08/2020 |
2.72 Cr. (Oct'22) 0.00 (Oct'22) |
work in progress by M/s Labotk |
Detail Report
Graph / Photo |
37 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. |
30.40 Cr. 02/09/2019 F.16/Estate/C/o Pucca School Building/Sec-27/PWD/4803-4809 |
31/05/2020 30/05/2021 31/12/2022 |
8.03 Cr. (Oct'22) 0.00 (Oct'22) |
WORK IN PROGRESS |
Detail Report
Graph / Photo |
S. No.क्र. सं. | Description | Details |
---|
S. No.क्र. सं. | Remarks | As On | Revised On |
---|
S. No.क्र. सं. | Upload Date | Description |
---|
S. No. | Date | Location | Remarks | Physical Progress (%) | View | ||
---|---|---|---|---|---|---|---|
Last | Upto | Photo | Doc |
S. No.क्र. सं. | Remarks | Date | Document |
---|
This is the Portal of Public Works Department, Govt. of NCT of Delhi, developed with an objective to enable a single window access to information and services being provided by the different wing of PWD Delhi. It is an initiative towards E-Governance Plan. यह लोक निर्माण विभाग, राष्ट्रीय राजधानी क्षेत्र (दिल्ली सरकार) का पोर्टल है जिसे इस उद्देश्य के साथ विकसित किया गया है जिससे लोक निर्माण विभाग, दिल्ली के विभिन्न स्कन्धों (विंग) द्वारा प्रदान की जा रही सूचनाओं तथा सेवाओं को एकल खिड़की के माध्यम से जाना जा सके | यह ई - गवर्नेंस योजना की दिशा में पहल है |
12th Floor, MSO Building,
I. P. Estate, New Delhi – 110002
Toll Free: 1800 11 00 93
© 2021 All Rights Reserved. Version 35.1.2 / 18-11-2023
This portal is designed, developed and maintained by M/s Calibre Websol Pvt. Ltd.
मैसर्स कैलिबर बेबसोल प्रा० लिमिटेड ने इस पोर्टल का विकास तथा अनुरक्षण / अभिकल्पन डिजाइन किया है
Session expire