Building Work
Cost more than 30 Cr.
Building : Work in Progress
S. No.क्र. सं. Project Name A/A & E/S Date of Start
Completion
Expected
Expenditure
Progress
Remarks View
1 C/o of 104 Nos. Additional SPS Class rooms, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangments etc. at SBV Keshav Puram (ID-1411029), SKV Keshav Puram A Block (ID-1411021) & SKV Bharat Nagar (ID-1411031). (Package-I) 2892.65 Cr.
14/08/2018
F-18/Estate/Constn. 12748 Eq. Cls/Priority-II/PWD/2975-80
29/12/2018
26/07/2019
30/11/2022
38.76 Cr. (Jul'22)
0.00 (Jul'22)
Work in progress Detail Report
Graph / Photo
2 RPVV Lajpat Nagar, School ID : 1925334 2892.65 Cr.
14/08/2018
(F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.)
08/12/2018
04/08/2019
31/10/2022
26.59 Cr. (Oct'22)
0.00 (Oct'22)
Work is in progress Detail Report
Graph / Photo
3 Co-Ed. SSS Lajpat Nagar, School ID: 1925335 2892.65 Cr.
14/08/2018
(F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.)
08/12/2018
04/08/2019
31/10/2022
0.00 Cr. (Sep'21)
60.00 % (Sep'21)
Work is in progress Detail Report
Graph / Photo
4 GBSSS Jungpura, School ID : 1924004 2892.65 Cr.
14/08/2018
(F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.)
08/12/2018
04/08/2019
31/10/2022
27.55 Cr. (Dec'21)
0.00 (Dec'21)
Work is in progress Detail Report
Graph / Photo
5 GGSSS Dera Village School ID: 1923023 2892.65 Cr.
14/08/2018
(F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.)
08/12/2018
04/08/2019
30/11/2022
17.39 Cr. (Oct'22)
0.00 (Oct'22)

In progress

Detail Report
Graph / Photo
6 GBSSS Dera Village School ID: 1923360 2892.65 Cr.
14/08/2018
(F.18/Estate/Const.12748 Equ.Cls/Priority-II/PWD/2975-80, Dtd 14.8.18Composite Sanction for Education Maintenance Zone for Rs. 2892.65 Cr.)
08/12/2018
04/08/2019
30/11/2022
0.00 Cr. (Feb'21)
63.00 % (Feb'21)

In progress

Detail Report
Graph / Photo
7 C/o of 244 Nos. Additional SPS Class rooms, MP Hall, Labs, toilets and Staircases i/c internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. at SKV Kanjhawala(School ID 1413025) , SV Jaunti ( School ID 1413181) and Govt. Co- ed Sr. Sec. School Nizampur (School ID 1413009 ) ( Package -09 ) 2892.65 Cr.
14/08/2018
F-18/Estate/Constn. 12748 Eq. Cls/Priority-II/PWD/2975-80
20/01/2019
15/11/2019
31/10/2022
38.84 Cr. (Oct'22)
0.00 (Oct'22)
Work in progress Detail Report
Graph / Photo
8 C/o 272 Nos. Additional SPS Class rooms i/c MP Hall, labs, toilets and Staircases, internal water supply, sanitary installation, drainage, electrical installation, development of site and fire fighting arrangements etc. Sector-16 Rohini (School ID: 1413070), GGSSS Sector-1 Avantika Rohini (School ID :1413069) & Sarvodaya Co-ed. Vidyalaya Sector-2 Rohini (School ID : 1413027) (Package-3) 2892.65 Cr.
14/08/2018
. F-18/Estate/Constn. 12748 Eq. Cls/Priority-II/PWD/2975-80
14/01/2019
09/11/2019
31/10/2022
47.00 Cr. (Oct'22)
0.00 (Oct'22)
Work in progress Detail Report
Graph / Photo
9 Construction of Hospital at Madipur, New Delhi 320.07 Cr.
06/12/2019
F.8(A)/(10)/DGHS/HC/2019/CD#112557061/Js3hfw-3999-4016
11/11/2020
10/11/2022
10/11/2022
43.72 Cr. (Oct'22)
0.00 (Oct'22)
RCC of terrace floor slab is completed. Masonry work at 8th & 9th floor is in progress. Finishing work such as tile work, granite work, POP, putty etc. in progress in 1st to 6th floor. Detail Report
Graph / Photo
10 Providing service of Photocopier Machine on rental basis in the Office of Executive Engineer, Health Project Division Central, PWD, Lok Nayak Hospital, New Delhi 320.07 Cr.
06/12/2019
F.8(A)/(10)/DGHS/HC/2019/CD#112557061/Js3hfw-3999-4016
--
--
--

work completed.. Detail Report
Graph / Photo
11 Providing service of Photocopier Machine on rental basis in the Office of Executive Engineer, Health Project Division (Central), PWD, Lok Nayak Hospital, New Delhi 320.07 Cr.
06/12/2019
F.8(A)/(10)/DGHS/HC/2019/CD#112557061/Js3hfw-3999-4016
--
--
--

work in progress. Detail Report
Graph / Photo
12 C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road, Delhi (SH: C/o Academic Blocks AB-3 & AB-4, Boys Hostel H-5 & Girls Hostels HG-5 & HG-6 and all external and internal services including external development and landscaping, and allied civil and E&M works). 291.88 Cr.
11/09/2018
75(8)/DTTE/Plg EFC/2013-14/000323618/527-33 dated 11.09.2018
23/09/2019
23/12/2020
16/10/2022
30.27 Cr. (Oct'22)
0.00 (Oct'22)
Boys Hostel and Girls Hostel has been completed. Academic Building is in final stage of completion. Work Provisionally completed on 27.09.2022 and handing over building is in progress. Detail Report
Graph / Photo
13 Construction of additional SPS type classrooms in Govt. Schools, Directorate of Education, under Priorty II.(Package-F) 289.27 Cr.
14/08/2018
( Consolidated sanction amount 2892.65 ) F-18/Estate/Cont. 12748 Egu.Cls/Priority-II/PWD/2975-80
27/01/2019
23/10/2019
31/10/2022
37.75 Cr. (Oct'22)
0.00 (Oct'22)

Work in progress.

Detail Report
Graph / Photo
14 Construction of Hospital at Hastsal, New Delhi 211.12 Cr.

17/06/2021
16/06/2023
16/06/2023

15% Detail Report
Graph / Photo
15 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 209.59 Cr.
27/11/2015
No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre)
25/01/2019
24/05/2019
30/09/2020
2.16 Cr. (Oct'21)
0.00 (Oct'21)
work in progress Detail Report
Graph / Photo
16 Construction of Aam Aadmi Mohalla Clinic (Primary Health Centre) at various places under North East Circle, PWD, Delhi 209.59 Cr.
27/11/2015
No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre)
27/12/2018
26/04/2019
--
3.36 Cr. (Aug'21)
0.00 (Aug'21)

work completed

Detail Report
Graph / Photo
17 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 194.91 Cr.
25/06/2018
2(11)/PWD-Upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45
04/03/2020
03/09/2021
03/09/2021
21.82 Cr. (Oct'22)
0.00 (Oct'22)
work in progress Detail Report
Graph / Photo
18 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 172.03 Cr.
22/06/2018
F.4/261/PWD/Health/2016/GGSH CD#112412717/2492-2509 dated 22.06.2018
18/10/2019
10/04/2021
12/12/2022
27.30 Cr. (Oct'22)
0.00 (Oct'22)
Work is under progress. Detail Report
Graph / Photo
19 Construction Of New 460 Bed Mother & Child Hospital Building At Khichripur , Delhi 143.73 Cr.
12/06/2019
A/A & E/S is issued by Sh. R.C. Kesarwani, Joint Secretary (H&FW) vide No. F.61/02/2006-07/Estt./LBSH/Pt. File CD#000384462/Jsshfw -1387-1405 dated 12
08/01/2020
01/04/2021
30/11/2022
6.76 Cr. (Oct'22)
0.00 (Oct'22)
Work was delayed mainly due to COVID-19 pandemic in 2020 & 21. MLCP structure above ground floor and connection of new building to existing building is to be decided. 7th & above floors casting in progress by parts. Detail Report
Graph / Photo
20 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 117.78 Cr.
22/06/2018
5/171/SGMH/TCSUB/CT/2016 CD# 112388502/2510-2527
04/09/2019
03/03/2021
31/12/2022
10.74 Cr. (Oct'22)
0.00 (Oct'22)
work in progress. Detail Report
Graph / Photo
21 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) 101.63 Cr.

18/07/2021
17/07/2022
17/07/2023
5.14 Cr. (Oct'22)
0.00 (Oct'22)
Work is in progress. Detail Report
Graph / Photo
22 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A6 Paschim Vihar, New Delhi (Package - 7). 101.63 Cr.

18/07/2021
17/07/2022
17/07/2023
0.00 Cr. (Sep'22)
0.00 (Sep'22)
Work is in progress. Detail Report
Graph / Photo
23 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 86.31 Cr.
23/03/2018
F. RTRMH-I/9/PWD(13)/2015-16/CD#000384488/1223-39
06/08/2019
29/10/2020
31/12/2022
6.02 Cr. (Oct'22)
0.00 (Oct'22)
Work is under progress. Detail Report
Graph / Photo
24 Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2) 83.39 Cr.
26/03/2018
F/10/Estate/Renovation of staff rooms/951 schools/DoE/945-50
--
--
--

Detail Report
Graph / Photo
25 Up gradation of one staffroom in 86 Nos. Schools under South-East Building Maintenance Division, Hauz Khas, New Delhi during 2018-19. (Civil and Electrical work). 83.38 Cr.
30/07/2018
Chief Engineer
23/03/2019
22/09/2019
22/09/2019
0.94 Cr. (Sep'22)
0.00 (Sep'22)
Work in progress Detail Report
Graph / Photo
26 Upgradation of 3 Nos staff rooms of GNCTD Schools under Jurisdiction of DHC Division PWD dg 2018 19 83.38 Cr.
26/03/2018
The A/A & E/S of Rs. 83,38,36,800/- has been received from Deptt. of Education vide letter no. F.16/Estate/Renovation staffrooms/951Schools/DoE/945-50
25/12/2018
22/02/2019
30/06/2019
0.18 Cr. (Nov'20)
0.00 (Nov'20)
Work in progress Detail Report
Graph / Photo
27 Upgradation of One Staff room in each of 951 Schools under Delhi Govt Sh Upgradation of staff rooms at various schools 25 Nos including Civil and Electrical works under CBMD M 323 Delhi Composite work 83.38 Cr.
26/03/2018
pl. Director of Education (Finance) vide letter No. F 16/Estate/Renovatin of Staff rooms/951 school/ DOE/945-50 dt. 26-03-2018 for Rs. 833836800/- Tot
--
--
--
0.28 Cr. (Aug'20)
0.00 (Aug'20)
Detail Report
Graph / Photo
28 Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). 83.38 Cr.
26/03/2018
F.16/estate/renovation of staff rooms/951 Schools/DOE/945-50 dated 26.03.2018 for Rs. 83,38,36,800/-
11/02/2019
10/06/2019
10/06/2019
5.40 Cr. (Jul'22)
0.00 (Jul'22)
WORK IN PROGRESS Detail Report
Graph / Photo
29 Upgradation/Renovation of one staff room in each of 73 schools (Morning and Evening Shift) located at (NE) District of Delhi under the jurisdiction of PWD Building Maintenance Division M-222 68.37 Cr.
26/03/2018
No. F.16/Estate/ Renovations of staff rooms/ 951 school/Dof/945-50 dated 26-3-2018
25/01/2019
24/04/2019
30/09/2019
1.93 Cr. (Jan'22)
0.00 (Jan'22)

work completed

Detail Report
Graph / Photo
30 Supplying, Installation, Testing and Commissioning of HVAC and Mechanical Ventilation system. (HVAC Package-2 68.00 Cr.
31/07/2013
7.73 Crores corresponding to this work
30/09/2014
26/05/2015
31/01/2016
0.61 Cr. (May'19)
0.00 (May'19)
Work completed on 31/12/2017 final payment yet to be made Detail Report
Graph / Photo
31 Construction of Pucca School building (G+3) with ancillary facilities including internal water supply, sanitary installations, internal electrical installation and development of site, RWHS, STP, Furniture etc at Sector 18, Rohini. (SH: Civil and Electrical Composite Work). 45.37 Cr.
02/09/2019
F.16/Estate/Const. Pucca School Building/Sector-18/Rohini/4824-4830
23/05/2020
23/05/2021
31/12/2022
12.28 Cr. (Oct'22)
0.00 (Oct'22)
Work in progress Detail Report
Graph / Photo
32 C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Daryapur kalan, Delhi. 43.70 Cr.
02/09/2019
F.16/Estate/Const.Pucca School Building/Dariyapur Kalan/4775-81
30/05/2020
29/05/2021
31/10/2022
0.00 Cr. (Nov'21)
30.00 % (Nov'21)
Structure work completed. Outsde clading work 90% completed. Outer development work like UG Tank and septic tank in progress.Coba work on terrace is in progress. Truss work of MP Hall completed and inside finishing in progress. Doors and window work in classroom in progress. Detail Report
Graph / Photo
33 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Dariyapur Kalan, Delhi 43.70 Cr.
02/09/2019
F.16/Estate/Const.Pucca School Building/Dariyapur Kalan/4775-81
30/05/2020
29/05/2021
31/10/2022
24.52 Cr. (Oct'22)
0.00 (Oct'22)
Structure work completed. Outsde clading work 90% completed. Outer development work like UG Tank and septic tank in progress.Coba work on terrace is in progress. Truss work of MP Hall completed and inside finishing in progress. Doors and window work in classroom in progress Detail Report
Graph / Photo
34 C/o Pucca School Building (Four Storeyed) with ancillary facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Libaspur, Delhi. 43.23 Cr.
02/09/2019
F.16/Estate/Const.Pucca School Building/Libaspur/4789-4795
30/05/2020
29/05/2021
31/10/2022
0.00 Cr. (Nov'21)
34.00 % (Nov'21)
Structure work completed. Partition work with bricks are completed. Tile, plaster and granite work is in progress. Truss work of MP Hall completed. Clading work on exterior wall is in progress. Plumbing work is in progress. Coba work on terrace is in progress. Construction of UG tank is in progress. Fixing of doors, windows and grill are in progress. Detail Report
Graph / Photo
35 Construction of pucca school building Four Storeyed with ancillary facilities incl. internal water supply, sanitary inst., internal elect. Inst. and dev. of site at Libaspur, Delhi 43.23 Cr.
02/09/2019
F.16/Estate/Const.Pucca School Building/Libaspur/4789-4795
30/05/2020
29/05/2021
31/10/2022
33.37 Cr. (Oct'22)
0.00 (Oct'22)
Structure work completed. Partition work with bricks are completed. Tile, plaster and granite work is in progress. Truss work of MP Hall completed. Clading work on exterior wall is in progress. Plumbing work is in progress. Coba work on terrace is in progress. Construction of UG tank is in progress. Fixing of doors, windows and grill are in progress. Detail Report
Graph / Photo
36 Expansion and Remodelling of Aruna Asaf Ali Govt. Hospital at Rajpur Road, New Delhi. 37.31 Cr.

10/08/2019
03/08/2020
03/08/2020
2.72 Cr. (Oct'22)
0.00 (Oct'22)
work in progress by M/s Labotk Detail Report
Graph / Photo
37 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 30.40 Cr.
02/09/2019
F.16/Estate/C/o Pucca School Building/Sec-27/PWD/4803-4809
31/05/2020
30/05/2021
31/12/2022
8.03 Cr. (Oct'22)
0.00 (Oct'22)
WORK IN PROGRESS Detail Report
Graph / Photo